HomeCost To CustomerM12898Evidence
Topic/Matter Intersection

Topic:"Cost To Customer" in M12898

Matter: Nova Scotia Power Inc. - Distribution Routines CI Various- D055 – Planned Replacement of Deteriorated Equipment (ATO) - $11,359,8222025 ACE Plan – Routine Capital - Authorization to Overspend (ATO):Distribution Routines – Non-Confidential • D055 – Planned Replacement of Deteriorated Equipment: ATO amount $11,359,822
3 passages 2 documents

Cost To Customer across all matters →

N-2NSPI (CA) RIR 1 to 12 - Redacted 2 passages
NSPI Responses to Consumer Advocate Information Requests p. p. 16
NSPI Responses to Consumer Advocate Information Requests 1 Request IR-2: 2 3 (a) Please provide a workbook in native format with a breakdown of project actual costs 4 by account compared to budget for all distribution routines for 2025. 5...

AI summary NSPI has been asked to provide detailed cost breakdowns for distribution routines in 2025 and over the past five years, including labour, contracts, materials, and administrative overhead. Additionally, NSPI is requested to explain the use of overtime labour for specific distribution routines, particularly in cases where the reason provided previously may not apply.

NON-CONFIDENTIAL p. p. 16
NON-CONFIDENTIAL 1 Request IR-4: Data provided in NSEB RIR-26, M12319, indicate that the average cost of a field driven work order increased from $1,481 in 2022 to $3,009 in 2023 and to $19,664 in 2024.

AI summary The average cost of a field driven work order increased significantly from $1,481 in 2022 to $19,664 in 2024, according to data provided in NSEB RIR-26, M12319.

103164Submissions - CA 1 passage
Preamble p. pp. 5-6
r Bin Work roughly doubled from 2023 to 2025. For the years 2022-2024, the cost per work order was in the range of $3,300 to $3,900. But then in 2025, the cost increased to over $7,000.[15](#page-5-2) It is unclear whether NS Power might s...

AI summary The cost per work order for Bin Work nearly doubled from 2023 to 2025, increasing from $3,300 to $3,900 in 2022-2024 to over $7,000 in 2025. NS Power claims the increase may be due to a broader range of work, but this is contradicted by its statement that Bin Work involves straightforward replacements. NS Power also lacks detailed data on Bin Work projects.

Disclaimer: These summaries were generated by AI from the filings they describe. We take care to make them accurate, but errors are possible - and they aren't advice. Only the filings themselves are the record: if you're relying on something here, confirm it against the source documents or the Nova Scotia Energy Board's own record. Full disclaimer →