DATE FILED: March 2, 2026 Page 17 of 29 p. pp. 16-18
DATE FILED: March 2, 2026 Page 17 of 29 1 10.0 DISPUTES 2 3 Section 2.8.2.1 of the Market Rules states: 4 5 2.8.2.1, Except as otherwise provided in respect of metering disputes, any disputes 6 under the Market Rules shall be subject to th...

AI summary The document outlines the absence of disputes in 2025 under the Transmission Tariff and discusses the reliability planning efforts, including an audit initiated by NPCC in 2024 that was extended due to a cyber-attack. The audit of NS Power covered 15 Standards and 33 Requirements.

N-2NSPI (NSEB) RIR 1 to 3 - Redacted 1 passage
BOARD CONFIDENTIAL (Attachment Only) p. p. 4
BOARD CONFIDENTIAL (Attachment Only) 1 Request IR-1: 2 3 On page 19, the report states that 4 5 6 7 "NPCC initiated a Critical Infrastructure Protection (CIP) and Operations & Planning (O&P) Audit on December 6, 2024, which continued into...

AI summary The document references a Critical Infrastructure Protection (CIP) and Operations & Planning (O&P) Audit conducted by NPCC, which was extended due to a cyber attack. The final audit report was provided in January 2026, and a request is made for a copy of the report covering a specific time period.

102974Decision letter 1 passage
M12725 – Nova Scotia Power Incorporated – 2025 Wholesale and Renewable to Retail Market Report p. p. 0
ee remains active, providing advice to NS Power on matters concerning these markets. It also confirmed that, in 2025, no temporary waivers were requested or granted, no compliance or Document: 332085 remedy issues arose, and no disputes oc...

AI summary The document discusses NS Power's compliance with market rules and audits conducted by the Northeast Power Coordinating Council (NPCC). It highlights the findings of a 2024 CIP and O&P audit, including ten PNCs, two areas of concern, and seven recommendations, as well as the resolution of issues from a 2022 audit. NS Power is addressing the findings and will report on the 2024 audit in its 2026 report.

101706NSEB (NSPI) IR 1 to 3 1 passage
Request IR-1:
Request IR-1: - On page 19, the report states that "NPCC initiated a Critical Infrastructure Protection (CIP) and - Operations & Planning (O&P) Audit on December 6, 2024, which continued into 2025." Due to - the cyber attack, NPCC extended...

AI summary NPCC extended a CIP and O&P audit due to a cyber attack, with the final report due in January 2026. The request is for a copy of this report covering a specific period.

102974Decision letter 1 passage
M12725 – Nova Scotia Power Incorporated – 2025 Wholesale and Renewable to Retail Market Report p. p. 0
ee remains active, providing advice to NS Power on matters concerning these markets. It also confirmed that, in 2025, no temporary waivers were requested or granted, no compliance or Document: 332085 remedy issues arose, and no disputes oc...

AI summary The document discusses NS Power's compliance with market rules and audits conducted by the Northeast Power Coordinating Council (NPCC) in 2022 and 2024. NS Power reported no compliance issues or disputes in 2025 and is addressing the findings from the audits. It also noted no outstanding reliability planning or outage management issues.

Disclaimer: These summaries were generated by AI from the filings they describe. We take care to make them accurate, but errors are possible - and they aren't advice. Only the filings themselves are the record: if you're relying on something here, confirm it against the source documents or the Nova Scotia Energy Board's own record. Full disclaimer →