Matter: Nova Scotia Power Dispatch Study Action Plan – Quarterly Update – Q1 2026
2 passages 1 document

Cybersecurity across all matters →

N-1Report 2 passages
Q1 2026 update – Project Go Live Delayed: p. pp. 3-4
Q1 2026 update – Project Go Live Delayed: - Encountered delays in interface testing due to vendor defect related to interface data flow capacity and changes made to vendor environment to boost their cyber security posture. - The delay in r...

AI summary The Q1 2026 update indicates that the project go live has been delayed due to vendor defects in interface data flow capacity and changes to the vendor's environment to enhance cybersecurity, leading to a drop in queue position and the need for significant re-testing.

Preamble p. pp. 4-5
- Cyber Event delayed this item - Requirements and design complete - Technical Realization completion ETA April 2026 - Testing, UAT and Training ETA May - Ready for ECCPO deployment schedule

AI summary The item was delayed due to a cyber event, with requirements and design completed. Technical realization is expected to be completed in April 2026, followed by testing, user acceptance testing, and training in May. It is now ready for deployment under the ECCPO schedule.

Disclaimer: These summaries were generated by AI from the filings they describe. We take care to make them accurate, but errors are possible - and they aren't advice. Only the filings themselves are the record: if you're relying on something here, confirm it against the source documents or the Nova Scotia Energy Board's own record. Full disclaimer →