Matter: Nova Scotia Power Inc. - CI C0082133 – IT-Renew Microsoft Enterprise Agreement- $1,987,3972026 Q1 Capital Reports
1 passage 1 document

Cybersecurity across all matters →

N-1CI C0082133 – IT-Renew Microsoft Enterprise Agreement- $1,987,397 - Redacted 1 passage
Table A.1 - Project Costs (CAPEX or OPEX) p. p. 1
Table A.1 - Project Costs (CAPEX or OPEX) Project Costs (gross) CAPEX 2026 2027 2028 2029 2030 2031 2032 2033 2034 2035 Current CyberArk on Prem licensing OPEX $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - Current PAM software upgrade/extension...

AI summary The table outlines project costs, including CAPEX and OPEX, for various cybersecurity-related initiatives. It includes entries for current licensing and software upgrade costs, though specific figures are not provided. The table spans from 2026 to 2035.

Disclaimer: These summaries were generated by AI from the filings they describe. We take care to make them accurate, but errors are possible - and they aren't advice. Only the filings themselves are the record: if you're relying on something here, confirm it against the source documents or the Nova Scotia Energy Board's own record. Full disclaimer →