P-1-(i)Appendix A - Green Choice PPA
4 passages
able, the Energy Bid will be prorated for any portion of a Contract Year. Contract Year – means a twelve-month period during the Term, starting on the Commencement Date or an anniversary thereof. Control – means (i) in relation to a Person...
AI summary The text defines key terms and concepts relevant to the Energy Bid, Contract Year, Control, Convention, CPI, and Cybersecurity Plan. These definitions are foundational for interpreting the agreement and regulatory requirements.
e Parties, NSPI shall have no property rights or interests with respect to the Project or the Site or any authority to affect or control any such activities which are the responsibility of the Seller. - (f) The Seller shall prepare a plan...
AI summary The Seller is required to prepare and submit a Cybersecurity Plan to the IESO, demonstrating compliance with NERC Critical Infrastructure Protection standards, at least six months before the Scheduled Commercial Operation Date. Failure to do so constitutes a Seller Event of Default and delays Commercial Operation.
2.4 Requirements for Commercial Operation (a) Notwithstanding the definition of "Commercial Operation Date" in the Generator Interconnection Agreement, the Facility will be deemed to have achieved " Commercial Operation " for the purposes...
AI summary The text outlines the requirements for a Facility to achieve Commercial Operation, including regulatory approvals, completion of construction, interconnection to the system, and submission of necessary reports. NSPI must confirm or contest the date of Commercial Operation within 10 business days of receiving notice from the Seller.
/span>(l) Commercial Operation has not occurred on or before the date which is 12 months after the Scheduled Commercial Operation Date (other than by reason of an occurrence of a Force Majeure Event). - (m) The Seller fails to obtain or ma...
AI summary The text outlines conditions for Seller Events of Default, including failure to achieve Commercial Operation within 12 months, failure to obtain or maintain Electricity Standard Approval, and failure to submit a Cybersecurity Plan by the deadline.
P-1-(ii)Appendix B - Green Choice PPA Blackline to PPA in M11455
4 passages
Cybersecurity Plan Submission Deadline is defined in Section 2.1(f). Daily Energy Bid – means, in respect of a Contract Year, the Energy Bid divided by the number of days in the Contract Year. Delivery Point – means the point of interconne...
AI summary The text defines key terms related to energy contracts and cybersecurity regulations, including the submission deadline for a cybersecurity plan, daily energy bid, delivery point, and dissolution event.
e Parties, NSPI shall have no property rights or interests with respect to the Project or the Site or any authority to affect or control any such activities which are the responsibility of the Seller. Infrastructure Protection standards pe...
AI summary The document outlines requirements for the Cybersecurity Plan related to the Project, which must be submitted to the IESO and NSPI six months before the Scheduled Commercial Operation Date. Failure to submit the plan on time constitutes a Seller Event of Default, and the Facility cannot achieve Commercial Operation until compliance with NERC Critical Infrastructure Protection standards is demonstrated.
2.4 Requirements for Commercial Operation - (a) Notwithstanding the definition of "Commercial Operation Date" in the Generator Interconnection Agreement, the Facility will be deemed to have achieved "Commercial Operation" for the purposes...
AI summary The document outlines the conditions for achieving commercial operation of a facility under the Generator Interconnection Agreement. Key requirements include approval from the Minister of the Environment, completion of the project, certification by an independent engineer, interconnection to the system, submission of a cybersecurity plan, and a local benefits report.
/span>(l) Commercial Operation has not occurred on or before the date which is 12 months after the Scheduled Commercial Operation Date (other than by reason of an occurrence of a Force Majeure Event). - (m) The Seller fails to obtain or ma...
AI summary This section outlines events of default related to the Seller's obligations under the agreement, including failure to achieve commercial operation within 12 months, failure to maintain Electricity Standard Approval, and failure to submit a Cybersecurity Plan by the deadline.
P-1-(iii)Appendix C - DRAFT #1 Green Choice PPA 2026 - CLEAN
4 passages
ship of securities or other interests entitling the holder to exercise direction over the activities of the Person (and " Controls ", " Controlling " and " Controlled " are defined accordingly). Convention – means United Nations Framework...
AI summary The text defines key terms and concepts relevant to the regulatory proceeding, including definitions of 'Control', 'Convention', 'CPI', 'Cybersecurity Plan', 'Daily Energy Bid', 'Delivery Point', and 'Dissolution Event', providing clarity for interpretation and application in the context of the proceeding.
s responsible for NSPI's reasonable legal expenses incurred in reviewing the Seller's request for consent in relation to any Project Amendment or any request for consent to amend the Commercial Terms. - (c) The Seller agrees to obtain and...
AI summary The document outlines the Seller's responsibilities regarding legal expenses, permits, interconnection, and cybersecurity for the Project. The Seller is responsible for design, development, construction, and compliance with NERC standards. Failure to submit a Cybersecurity Plan on time is considered a default.
2.4 Requirements for Commercial Operation - (a) Notwithstanding the definition of "Commercial Operation Date" in the Generator Interconnection Agreement, the Facility will be deemed to have achieved " Commercial Operation " for the purpose...
AI summary The document outlines the requirements for achieving Commercial Operation for a Facility under the Generator Interconnection Agreement. It includes conditions such as environmental approval, completion of the project, interconnection to the System, submission of a Local Benefits Report, and approval of the Cybersecurity Plan.
emedied within 30 days after written notice of such breach from NSPI or, if the breach cannot be remedied within such 30 day period, the Seller fails to demonstrate to the satisfaction of NSPI, acting reasonably, that the Seller is diligen...
AI summary This section outlines the conditions under which a Seller may be in default, including failure to remedy breaches within specified timeframes, failure to achieve Commercial Operation by certain dates, failure to obtain Electricity Standard Approval, and failure to submit a Cybersecurity Plan by the deadline.