Matter: Nova Scotia Power Inc. - CI C0085287 – IT - Cybersecurity Standard Integrated Platform Program - $1,941,520 (U&U)
9 passages 2 documents

Cybersecurity across all matters →

N-1CI C0085287 – IT - Cybersecurity Standard Integrated Platform Program - Application - Redacted 8 passages
REDACTED (CONFIDENTIAL INFORMATION REMOVED)
REDACTED (CONFIDENTIAL INFORMATION REMOVED) CI C0085287 IT - Cybersecurity Standard Integrated Platform Program REDACTED October 5, 2026 REDACTED (CONFIDENTIAL INFORMATION REMOVED) NSEB APPROVAL SHEET Project Title: IT - Cybersecurity Stan...

AI summary The document is an NSEB approval sheet for the IT - Cybersecurity Standard Integrated Platform Program, submitted by Nova Scotia Power Incorporated. It includes expenditure details, authorization for unforeseen and unbudgeted costs, and approval dates.

Title: IT - Cybersecurity Standard Integrated Platform Program
Title: IT - Cybersecurity Standard Integrated Platform Program Start Date: 2026/07 In-Service Date: 2026/10 Final Cost Date: 2027/10 Function: General Plant Forecast Amount: $1,941,520

AI summary The document outlines a cybersecurity standard integrated platform program with a start date in July 2026, an in-service date in October 2026, and a final cost date in October 2027. The forecasted amount for the program is $1,941,520.

DESCRIPTION:
DESCRIPTION: This project will implement as NS Power's primary cybersecurity platform for the IT environment and transition away from several legacy tools and services, including and The work includes the planning, design, implementation,...

AI summary This project involves implementing a new cybersecurity platform for NS Power's IT environment, replacing legacy tools to improve visibility, threat intelligence, response times, and risk management. The transition includes retiring overlapping tools and establishing a standardized cybersecurity model, with specialized solutions retained where necessary. OT implementation is excluded and will be handled separately.

JUSTIFICATION:
JUSTIFICATION: Justification Criteria: Information Technology Application and Hardware System Sub-Criteria: Technical

AI summary The justification criteria focus on the technical aspects of information technology application and hardware systems, indicating a regulatory consideration of technological implementation.

Why do this project?
Why do this project? NS Power needs to complete this project because cybersecurity threats continue to increase in volume and sophistication, including threats supported by agentic AI, and generative AI. The current cybersecurity environme...

AI summary NS Power is undertaking a cybersecurity project to address increasing threats from AI-supported attacks. The project aims to enhance threat intelligence, detection, and response capabilities, reduce operational complexity, and improve continuous visibility into cyber risks through integrated platforms and standardized technology.

Why do this project now?
Why do this project now? Several critical cybersecurity tool licenses and services expired on September 30, 2026, requiring a decision on the future direction of the cybersecurity technology portfolio. Rather than renewing a collection of...

AI summary This project aims to replace expired cybersecurity tools with an integrated platform to improve threat intelligence and reduce costs. Proceeding now avoids overlapping technologies and supports enhanced capabilities, while deferring risks outdated tools being outpaced by AI-enhanced attacks.

Why do this project this way?
Why do this project this way? NS Power considered whether to continue with the existing cybersecurity operating model by renewing the current tools and services. While this option would reduce near-term implementation effort, it would main...

AI summary NS Power evaluated options for its cybersecurity strategy, considering renewal of current tools versus implementing a platform-based solution. The latter was recommended for its ability to enhance threat response, integration, and operational efficiency, particularly in light of advancements in AI-driven cyber threats.

Document No: XXX-XX-XXXX-XXXX
Document No: XXX-XX-XXXX-XXXX Project Cost Estimate Input Checklist and Maturity Matrix Equipment Replacement Required fields: Estimate Classification Project Name: IT - Cybersecurity Standard Integrated Platform Program Maturity Level of...

AI summary The document provides a checklist and maturity matrix for the IT - Cybersecurity Standard Integrated Platform Program, detailing the project's scope, requirements, and deliverables. It includes classifications for estimate maturity levels and the status of various project components such as hardware, codes, standards, and regulatory approvals.

103794Letter NS Power re: Capital Items Filed Outside the Quarter Package & Request for Confidentiality 1 passage
Third Party Information/Proprietary Information
Third Party Information/Proprietary Information Item 4 : The vendor has requested confidentiality of cost support (Attachment 1) for this capital work order. This information is considered proprietary and commercially sensitive by the vend...

AI summary The vendor has requested confidentiality for cost support information in a capital work order due to its proprietary and commercially sensitive nature. NS Power has also applied confidentiality to technical IT system details and system operating diagrams to protect against security threats and ensure system reliability.

Disclaimer: These summaries were generated by AI from the filings they describe. We take care to make them accurate, but errors are possible - and they aren't advice. Only the filings themselves are the record: if you're relying on something here, confirm it against the source documents or the Nova Scotia Energy Board's own record. Full disclaimer →