Matter: CI# 39323; CI# 39626; CI# 39627; & CI# 39628 - P-128.10 - NSPI WO - (Digby Wind Project) Application for approval of capital work orders  in the amount of $82.8 million for the acquisition, construction and interconnection of the Digby Wind Farm Project
6 passages 3 documents

Dcrr across all matters →

N-3-(b)Redacted NSPI Response to UARB IR-12 (att 7-10) to IR-17 4 passages
Section 2453 p. p. 3
- .2 CSA Standards - .1 C156.1, Ceramic and Glass Station Post Insulators - .2 G164, Hot Dipped Galvanized or Irregularly Shaped Articles - .3 W59, Welded Steel Construction (metal-ark welding) - .3 NEMA Standards - .1 Std. SG-6, Power Swi...

AI summary This document outlines the standards and submittal requirements for electrical components, including CSA, NEMA, ANSI/IEEE, and ISO standards, as well as specifications for operation and maintenance data and manufacturer drawings for disconnect switches.

1.9 Connection Transformer(s) p. pp. 80-81
2.1 The overall assembly enclosure(s) shall provide protection from ingress of rodents, insects, and moisture; and the possibility of arcing faults within the enclosure. - 1.12.2 The material for all external sides of the enclosure and int...

AI summary The document outlines technical specifications for the assembly enclosures, including protection against environmental factors, material requirements, grounding provisions, environmental control, and fire suppression capabilities.

9 IN-PLANT INSPECTION AND TESTING p. pp. 110-111
9 IN-PLANT INSPECTION AND TESTING - 9.1 The Owner, Purchaser, Engineer, and/or their authorized agents shall have the privilege of inspecting and witnessing all testing at all times during the manufacture of the equipment or materials orde...

AI summary This section outlines the requirements for in-plant inspection and testing during equipment manufacturing, including the right to inspect, advance notice requirements, and the submission of test results to the Engineer.

Section 3458 p. p. 160
- .8 Formwork: - .1 Forms: to CSA-A23.1, plywood and lumber, clean and free of loose knots, splits or metal. - .2 Form Ties: to CSA-A23.1, removable or snap-off metal ties, fixed or adjustable length. Form ties, tie wire, spacers or other...

AI summary The text outlines specifications for formwork and concrete mix, referencing various Canadian standards and testing methods. It details requirements for materials such as form ties, release agents, and curing compounds, as well as specifications for concrete mix proportions and air content.

06537Board Decision 1 passage
Submissions - Intervenors p. p. 0
Submissions - Intervenors [89] The CA argued that there was a failure on the part of NSPI to determine that the EUS contract was the best option available. He submitted: According to the evidence, EUS must have begun work by either the end...

AI summary The CA argues that NSPI failed to properly evaluate the EUS contract, which was selected without proper negotiation and based on a price picked from the market range. The CA also claims that NSPI did not investigate whether the contract price could be reduced and did not confirm that the EUS price excluded markups by EUS on subcontractor charges.

06537Board Decision 1 passage
Submissions - Intervenors p. p. 0
Submissions - Intervenors [89] The CA argued that there was a failure on the part of NSPI to determine that the EUS contract was the best option available. He submitted: According to the evidence, EUS must have begun work by either the end...

AI summary The CA criticized NSPI for failing to properly evaluate the EUS contract, arguing that the price was not negotiated but 'picked' based on market range without sufficient analysis. NSPI did not investigate potential bid reductions from other bidders or verify if the EUS price included markups by subcontractors.

Disclaimer: These summaries were generated by AI from the filings they describe. We take care to make them accurate, but errors are possible - and they aren't advice. Only the filings themselves are the record: if you're relying on something here, confirm it against the source documents or the Nova Scotia Energy Board's own record. Full disclaimer →