N-6NSPI (IG) RIR 1 to 31 - Redacted 4 passages
FOR SEPTEMBER 2027 p. p. 181
FOR SEPTEMBER 2027 (1) MWH SALES (2) ENERGY LINE LOSSES (3) ENERGY REQUIREMENT (4) CLASS NON- COINCIDENT DMD. (KW) (5) SYSTEM COINCIDENT FACTOR (6) SYSTEM COINCIDENT DMD. (KW) (7) DEMAND LINE LOSSES (8) SYSTEM COIN. PEAK DMD. (KW) (9) SYST...

AI summary The text presents a table with various metrics related to energy sales, losses, demand, and system factors for September 2027. It includes columns such as energy sales, energy losses, energy requirement, demand factors, and system peak demand. The table appears to be part of a regulatory proceeding related to energy billing and real-time pricing.

FOR THE YEAR ENDING DECEMBER 31, 2027 p. p. 181
FOR THE YEAR ENDING DECEMBER 31, 2027 (1) MWH (2) ENERGY LINE (3) ENERGY SALES LOSSES REQUIREMENT DMD. (KW) (4) CLASS NON- SYSTEM (5) COINCIDENT COINCIDENT COINCIDENT FACTOR (6) SYSTEM DEMAND SYSTEM (7) LINE (8) DMD. (KW) LOSSES DMD. (KW)...

AI summary The document presents a table with various metrics related to energy distribution and transmission for the year ending December 31, 2027, including values for MWH, energy line, system demand, and losses. It includes data on different categories such as substations, distribution, and transmission.

FOR THE YEAR ENDING DECEMBER 31, 2026 p. p. 181
FOR THE YEAR ENDING DECEMBER 31, 2026 (1) MWH SALES (2) ENERGY LINE (3) ENERGY LOSSES REQUIREMENT DMD. (KW) (4) CLASS NON- SYSTEM (5) FACTOR (6) SYSTEM DEMAND SYSTEM COINCIDENT COINCIDENT COINCIDENT LINE COIN. PEAK COINCIDENT (7) (8) (9) S...

AI summary The document presents a table related to energy sales, losses, demand, and contribution percentages for the EHV Transmission Service as of December 31, 2026. It includes metrics such as MWH sales, energy losses, system demand, and 3CP contribution percentages.

FOR MARCH 2026 p. p. 181
FOR MARCH 2026 (1) MWH SALES (2) ENERGY LINE LOSSES (3) ENERGY REQUIREMENT (4) CLASS NON- COINCIDENT DMD. (KW) (5) SYSTEM COINCIDENT FACTOR (6) SYSTEM COINCIDENT DMD. (KW) (7) DEMAND LINE LOSSES (8) SYSTEM COIN. PEAK DMD. (KW) (9) SYSTEM C...

AI summary The document presents a summary of energy sales, losses, and demand metrics for March 2026, including total MWH sales, energy line losses, energy requirement, and system demand factors.

N-23RIRs filed from M12768 - NSPI (IG) RIR 1 to 15 - (Filed as N-3 in Matter M12768) - Redacted 1 passage
2025 ELIADC IG IR-3 Attachment 1 Page 5 of 7 REDACTED (CONFIDENTIAL INFORMATION REMOVED) p. p. 10
2025 ELIADC IG IR-3 Attachment 1 Page 5 of 7 REDACTED (CONFIDENTIAL INFORMATION REMOVED)

AI summary The document is a redacted attachment from a 2025 ELIADC IG IR-3 proceeding, indicating that confidential information has been removed. It likely contains details related to the Extra Large Industrial Active Demand Control program and its implications for Nova Scotia's energy sector.

Disclaimer: These summaries were generated by AI from the filings they describe. We take care to make them accurate, but errors are possible - and they aren't advice. Only the filings themselves are the record: if you're relying on something here, confirm it against the source documents or the Nova Scotia Energy Board's own record. Full disclaimer →