Summary of Related CIs +/- 2 years:
p. p. 1
Summary of Related CIs +/- 2 years: Pursuant to Section 11.2 of the CEJC, related CIs for Steam projects includes "work completed on the same asset (turbine, boiler, etc.) and on the same unit (Lingan Unit #3, for example)." - 2023 C005229...
AI summary The document lists capital improvement projects (CIs) for Steam Production Plant – Point Aconi under Section 11.2 of the CEJC, including boiler refurbishments, replacements, and upgrades from 2023 to 2027, with associated costs and depreciation classifications.