Summary of Related CIs +/- 2 years: p. p. 1
Summary of Related CIs +/- 2 years: Pursuant to Section 11.2 of the CEJC, related CIs for General Plant projects include "work completed on the same asset (application, building, etc.)." • No other projects in 2023, 2024, 2025, 2026, or 20...

AI summary The document outlines the depreciation class for General Plant – Computer Application Software, with an estimated asset life of 10 years. No projects were completed in 2023 to 2027, except those related to work on the same asset.

N-3NSPI (NSEB) RIR 1 to 15 - Redacted 1 passage
Active Submissions p. p. 23
Active Submissions Total A - Technical Evaluation A-1 - Adherence to RFP requirements A-2 - Ongoing support availability and service levels A-3 - Speed and efficiency of implementation (or project) plan, availability, and delivery the indu...

AI summary The text outlines the structure of an evaluation matrix for submissions, focusing on technical evaluation criteria such as adherence to RFP requirements, ongoing support, implementation speed, and industry expertise. It also includes sections related to corporate risk, including cybersecurity, insurance, and third-party attestation.

N-4NSPI (REI) RIR 1 to 22 1 passage
Date Filed: March 3, 2026 NSPI (REI) IR-13 Page 3 of 3 p. p. 36
Date Filed: March 3, 2026 NSPI (REI) IR-13 Page 3 of 3 1 Request IR-14: D.27 Business Process & Procedure Development Team has finalized process and procedure documentation from a Role Based perspective. Business Leads have all signed off...

AI summary The document outlines several tasks related to the final stages of a project, including the completion of business process documentation, technical development, and testing. These tasks are currently at various stages of completion, with some already finalized and others not yet started.

Disclaimer: These summaries were generated by AI from the filings they describe. We take care to make them accurate, but errors are possible - and they aren't advice. Only the filings themselves are the record: if you're relying on something here, confirm it against the source documents or the Nova Scotia Energy Board's own record. Full disclaimer →