Matter: Nova Scotia Power inc. - CI C0084033 – RC SCR Bridge 10.10 Refurbishment - $1,008,9412026 Q1 Capital Reports
1 passage 1 document

Depreciation Amortization across all matters →

N-1CI C0084033 – RC SCR Bridge 10.10 Refurbishment - $1,008,941 - Redacted 1 passage
Summary of Related CIs +/- 2 years: p. p. 1
Summary of Related CIs +/- 2 years: Pursuant to Section 11.2 of the CEJC, related CIs for Steam projects include "work completed on the same asset (turbine, boiler, etc.) and on the same unit (Lingan Unit #3, for example)." - 2024 C0063409...

AI summary The document lists capital improvement (CI) projects for the Steam Production Plant Lingan, including specific projects with costs and depreciation details. The depreciation class is 'Steam Production Plant Lingan - Common' with an estimated asset life of 20 years.

Disclaimer: These summaries were generated by AI from the filings they describe. We take care to make them accurate, but errors are possible - and they aren't advice. Only the filings themselves are the record: if you're relying on something here, confirm it against the source documents or the Nova Scotia Energy Board's own record. Full disclaimer →