N-1Application - Redacted
31 passages
centre, as required to fulfil - the organization's mandate under the MAEA, enable independent Balancing Authority - (BA)/Transmission Operator (TOP) operations, and create defined physical and cyber - boundaries - Phase 2B Introduces provi...
AI summary IESO Nova Scotia is seeking Board approval for capital costs associated with Phase 2A ($40.91 million) and Phase 2B ($8.08 million) of the Phase 2 Control Centre project, along with forecast amortization for Phase 2A. These phases aim to fulfill mandates under the More Access to Energy Act (MAEA), including enabling independent Balancing Authority/Transmission Operator operations and establishing physical and cyber boundaries. Phase 2C, which focuses on grid optimization and an independent Energy Management System, is being deferred to allow for further validation and refinement based on future operating experience.
1.4 Process - This Application reflects a more detailed budgeting process than was possible for IESO Nova - Scotia's first two revenue requirement applications. The organization has developed three - annual budgets within approximately 18...
AI summary IESO Nova Scotia describes the evolution of its budgeting process, moving from high-level estimates to a detailed bottom-up approach for the 2027/2028 budget. The process integrates OM&A budgets with capital plans to ensure the revenue requirement reflects asset timing, amortization, and financing costs. Key improvements include revised OM&A cost categories to align with functional departments and the provision of multi-year indicative outlooks for 2028-2030 in response to Nova Scotia Energy Board requirements.
14 Figure 1: NSEB Direction NSEB Directive IESO Nova Scotia Response Accounting Policies Attached in Appendix 1 "The Net OM&A Deferral and Variance Account is approved. However, specific guidelines and accounting policies must be developed...
AI summary The document outlines a specific Nova Scotia Energy Board (NSEB) directive regarding the Net OM&A Deferral and Variance Account (DVM). While the account is approved, the Board requires IESO Nova Scotia to develop and submit specific guidelines, accounting policies, and financial controls before any recovery of Net Ongoing OM&A amounts can occur. IESO Nova Scotia responds that its accounting policies, which govern capital expenditures and depreciation, have been finalized and are submitted for review to support the approval of variances under the DVM.
1.8 Structure of the Application - The balance of the Application is structured as follows: - Section 2: IESO Nova Scotia Business Plan and Linkage to Proposed Expenditures and Revenue Requirement - Section 3: Proposed Expenditures and Rev...
AI summary This section outlines the organizational structure of the application submitted by IESO Nova Scotia. It details the content of six main sections, including the business plan's linkage to expenditures, specific proposed expenditures for the Phase 2 Control Centre project, amortization of IT and capital assets, and operational expenses (OM&A). Additionally, it covers the calculation of fees based on the revenue requirement and the specific reliefs sought from the Nova Scotia Energy Board.
ies, and carry out the other functions - necessary to operate as an independent energy system operator. - The proposed capital expenditures for Phases 2A and 2B of the Control Centre project are the - principal costs associated with this p...
AI summary IESO Nova Scotia outlines its capital expenditures and operational priorities for the 2026/2029 fiscal years, specifically focusing on the Control Centre project (Phases 2A and 2B). The project involves approximately $48.99 million in capital work in progress to establish an independent energy system operator model, including cybersecurity and reliability compliance. Additionally, the entity emphasizes its mandate to plan and procure electricity resources to maintain system reliability, aiming to complete its first Integrated Resource Plan by 2027/2028.
2. Amortization and financing-related costs These expenses reflect the use of capital assets in delivering IESO Nova Scotia's mandate, including information technology assets and one month of depreciation associated with Control Centre ass...
AI summary The text describes amortization and financing-related costs associated with IESO Nova Scotia's mandate. These costs include the utilization of capital assets, specifically information technology assets and one month of depreciation for Control Centre assets scheduled for March 2028. Additionally, the text notes that these expenses account for the financing arrangements necessary for a not-for-profit organization to execute a significant capital program in the absence of shareholder funding.
over projected operation, maintenance and administrative expenses, amortization expenses, taxes and payments in lieu of taxes, interest and other financing expenses, and a reasonable return on equity; - To date, IESO Nova Scotia has applie...
AI summary The text discusses the distinction between 'revenue requirement' and 'proposed expenditures' under the More Access to Energy Act (MAEA). It clarifies that while revenue requirements include OM&A expenses, taxes, and amortization, they do not include capital work in progress (CWIP). Because CWIP is not eligible for recovery through rates or fees, it must be sought as a proposed expenditure under s.29 of the MAEA. Specifically, IESO Nova Scotia is seeking Board approval for CWIP related to its Phase 2 Control Centre build-out.
3.1.1 Summary of Proposed Expenditures and Revenue Requirement - The Application includes the following costs associated with Proposed Expenditures and - Revenue Requirement: - Proposed Expenditures associated with: - o capital costs (capi...
AI summary The Application outlines proposed expenditures and the revenue requirement for IESO Nova Scotia, specifically focusing on the Phase 2 Control Centre Project. It seeks approval for $48.99M in capital work in progress (CWIP) for 2026-2030. The 2027/2028 revenue requirement of $15.19M includes amortization for the Control Centre and other IT assets, alongside $14.76M in ongoing OM&A costs. OM&A costs are projected to decrease slightly due to the conclusion of the current IRP process and lower consulting costs, offset by higher interest expenses and public education costs.
3.3 Amortization - This Application is the first to include amortization related to IESO Nova Scotia capital assets. - Amortization is related to the allocation of costs over the useful life of tangible and intangible - assets. As a System...
AI summary The text introduces the amortization of capital assets for IESO Nova Scotia, noting that this application is the first to include such costs. While IESO Nova Scotia does not typically have large capital expenditures like generation or transmission owners, it incurs costs for projects like the Phase 2 Control Centre and various IT assets. The amortization rates and treatment for these tangible and intangible assets are governed by the organization's accounting policy for Property, Plant and Equipment and Intangible Assets.
1 3.3.1 Phase 2 Control Centre 2 As described above in section 3.2 regarding the Phase 2 Control Centre project, Phase 2A 3 regarding system operational dispatch functionality, and the corresponding control centre 4 assets, are expected to...
AI summary The text describes the Phase 2 Control Centre project, noting that the Phase 2A system operational dispatch functionality and associated assets (including buildings, hardware, and software) are expected to be in-service by March 2028. Because of this timeline, one month of amortization expense is included in the current revenue requirement. These investments align with IESO Nova Scotia's strategic priority to complete the successful transition of system operations.
11 Figure 12: Control Centre Amortization Budget Amortization Budget (MS) Estimated Capital Cost Amortization Period (years) 2027/2028F $15. 95 20 $0.06 $5.41 5 $0.09 $10.03 5 $0.15 $9.52 10 $0.08 $40.91 $0.38 12
AI summary The document presents a table detailing the amortization budget for a Control Centre. It breaks down the estimated capital costs and corresponding amortization periods for five distinct components, totaling an estimated capital cost of $40.91 million. The amortization values for the 2027/2028 forecast period are provided for each component, ranging from $0.06 million to $0.38 million.
13 Further details regarding the costs budgeted as part of this cost category are as follows: 14 Building: This involves the design, construction, renovation, fit-out, and commissioning of IESO 15 Nova Scotia's independent Control Centre....
AI summary The text outlines the budgeted costs for IESO Nova Scotia's independent Control Centre as part of a Phase 2 project. It details four primary cost categories: building construction and office space (20-year depreciation), computer hardware for IT and OT infrastructure (5-year depreciation), software solutions for market activities and system operations (5-year depreciation), and regulatory compliance costs to meet NERC standards (10-year amortization). All estimates are based on an IBM Report and align with IESO Nova Scotia's accounting policies.
1 3.3.2 Information Technology 2 Separate from the assets deployed in the Control Centre, IESO Nova Scotia will also need to 3 implement software and hardware assets to enable additional existing business functions. As 4 more employees are...
AI summary IESO Nova Scotia identifies necessary investments in information technology (IT) and operational technology (OT) to support its foundational business functions and strategic priorities. This includes the procurement of hardware, such as computers and mobile devices, to accommodate new employees, as well as a specific software solution to manage transmission interconnection activities. The text emphasizes that these IT expenditures are essential for the organization's core operations and includes an amortization budget for these assets.
9 Figure 13: IT Amortization Budget Amortization Budget ($) Cost Category Estimated Capital Cost Amortization Period (years) 2027/2028F Computers $0.06 5 $0.01 Software $0.43 5 $0.04 Total $0.50 $0.05 10
AI summary The document provides a table outlining the IT Amortization Budget for the 2027/2028 forecast period. It breaks down the estimated capital costs and amortization periods for computers and software. The total estimated capital cost for these categories is $0.50 million with a 5-year amortization period, resulting in a total amortization budget of $0.05 million for the 2027/2028 forecast year.
10 3.5 2027 – 2030F Outlook - 11 Pursuant to the NSEB's direction in M12412, this section provides IESO Nova Scotia's three years - 12 of projected financial results. Figure 27 below provides 2027/2028F, 2028/2029F, and - 13 2029/2030F for...
AI summary IESO Nova Scotia provides a three-year financial outlook for the 2027–2030 period, including projected expenditures, amortization, and OM&A total costs. The company notes that as a newly established not-for-profit entity with less than a year of operational experience, the accuracy of outer-year forecasts is subject to change due to the lack of historical operational data.
19 Figure 27: 2027-2030F Outlook Category 2027/2028F Total Budget 2028/2029F Total Budget 2029/2030F Total Budget Proposed Expenditures $27.5 $6.7 $4.8 Revenue Requirement $15.23 $34.7 $37.6 Amortization $0.43 $4.7 $5.8 OM&A $14.8 $30.0 $3...
AI summary The document presents a financial outlook for the 2027-2030 forecast period, specifically highlighting the budget categories for Proposed Expenditures, Revenue Requirement, Amortization, and Operating, Maintenance and Administration (OM&A) costs. The data shows a significant increase in the Revenue Requirement and OM&A costs from 2027/2028F to 2029/2030F, while Proposed Expenditures are projected to decrease significantly over the same period.
4.2 OM&A and Amortization - Consistent with section 29 of the MAEA, IESO Nova Scotia's revenue requirement represents the - costs necessary to carry out its statutory mandate and forms the basis for recovery through the - proposed Fee Reco...
AI summary The text outlines the components of IESO Nova Scotia's revenue requirement under the More Access to Energy Act (MAEA). It specifies that the revenue requirement consists of Operating, Maintenance and Administration (OM&A) costs and amortization expenses for capital assets. These costs are eligible for recovery through the proposed Fee Recovery Mechanism. Specifically, the OM&A reflects ongoing operational costs for the 12-month application period, while amortization includes costs for Control Centre assets and various IT assets.
1 Figure 28 - Control Centre Amortization Control Centre Costs Cost Amortization Rate (Years) Annual Amortization 2027-2028 Amortization (1 month) Building $15.08M 20 $0.75M $0.06M Computers and Software $1 4.60M 5 $2.92M $0.24M Licenses $...
AI summary The document provides a cost breakdown and amortization schedule for the Control Centre. It details capital costs for buildings, computers, software, and licenses, totaling $38.68 million. The table specifies respective amortization periods ranging from 5 to 20 years, with an annual amortization total of $4.57 million. It also calculates the specific amortization for a one-month period in the 2027-2028 fiscal year.
- 3 Total amortization for the 2027-2028 fiscal year, inclusive of other IT assets, is estimated as - 4 shown in Figure 29 below.
AI summary The document provides a brief financial estimate regarding the total amortization for the 2027-2028 fiscal year. This figure is inclusive of other Information Technology (IT) assets and is visually represented in Figure 29 of the filing.
5 Figure 29 - Total Amortization for all Capital Capital Additions Cost Amortization Rate (Years) Annual Amortization 2027-2028 Amortization Computer Hardware $0.06M 3-5 $0.01M $0.01M Perpetual Software $0.43M 5-7 $0.09M $0.04M Control Cen...
AI summary The document presents a table detailing the amortization schedule for various capital additions, including computer hardware, perpetual software, and a control centre. It specifies the total capital cost of $39.18M, the respective amortization rates ranging from 3 to 12 years, and calculates the annual and 2027-2028 specific amortization amounts. The control centre represents the largest portion of the capital additions, accounting for the majority of the annual amortization.
4.3 Net Revenue Requirement Deferral and Variance Account - IESO Nova Scotia seeks approval of its 2025/2026 fiscal year variance by way of the net Revenue - Requirement Deferral and Variance Mechanism (DVM). Notwithstanding the fact NSEB...
AI summary IESO Nova Scotia is seeking approval for its 2025/2026 fiscal year variance using the Net Revenue Requirement Deferral and Variance Mechanism (DVM). Although DVM approval is pending under a separate proceeding (M12663), the variance calculation remains consistent with the OM&A Deferral and Variance Account. The DVM is designed to track differences between forecasted and actual revenue requirements—including OM&A and amortization—to ensure market participants pay amounts reflecting actual costs through future true-up fee adjustments.
4.4 Fee Calculation for Fiscal Year 2027/2028 - IESO Nova Scotia's fees for fiscal year 2027/2028 have been calculated based on the revenue - requirements described above in this Application. Namely, the OM&A and amortization expense - of...
AI summary IESO Nova Scotia has calculated its fees for fiscal year 2027/2028 based on revenue requirements, specifically OM&A and amortization expenses totaling $15.19M. The calculations were performed by Power Advisory using a model derived from the Fee Recovery Mechanism application (M13007). Because a final decision on M13007 is pending, IESO Nova Scotia provided fee calculations for Load Serving Entities based on two different True-Up Options.
Purpose The purpose of this policy is to establish consistent criteria for the capitalization, depreciation, and disposal of Property, Plant and Equipment (PP&E) and Intangible Assets in accordance with the IESO Nova Scotia accounting fram...
AI summary The document outlines the purpose of a policy designed to establish consistent criteria for managing Property, Plant and Equipment (PP&E) and Intangible Assets. Specifically, it addresses the standards for capitalization, depreciation, and disposal of these assets to ensure alignment with the IESO Nova Scotia accounting framework.
Measurement and Useful Life Property, plant and equipment are recorded at cost less accumulated depreciation. Cost includes the purchase price, plus any additional costs directly attributable to the construction of the asset and preparing...
AI summary The text outlines the accounting treatment for property, plant, and equipment (PP&E). Assets are recorded at cost, including purchase price, construction costs (materials, payroll, consulting, borrowing), and asset retirement costs. Construction in progress is tracked until completion, at which point it is transferred to the appropriate category. Maintenance costs that do not extend asset life are expensed. Depreciation is calculated using the straight-line method over estimated useful lives, with annual reviews of these parameters.
Depreciation periods for property, plant and equipment are shown in the following table. Computer and Audio-Visual Hardware Straight line 3-5 years Furniture and Fixtures Straight line 10 years Leasehold Improvements Straight line 10 years...
AI summary The document outlines the depreciation schedules for various categories of property, plant, and equipment (PP&E). It specifies straight-line depreciation periods for items such as computer hardware (3-5 years), furniture and fixtures (10 years), and buildings (20-40 years), while noting that land and construction in progress are not depreciated. Additionally, it establishes the criteria for asset retirement, stating that assets are retired upon full depreciation and derecognized when disposed of or no longer providing future benefits.
Measurement and Useful Life Intangible assets are recorded at cost less accumulated amortization. Cost includes the purchase price, plus any additional costs directly attributable to the development of the asset and preparing the asset for...
AI summary The text outlines the accounting policies for intangible assets, stating they are recorded at cost minus accumulated amortization. Costs include purchase price, development, payroll, consulting, and borrowing costs. Maintenance and repair costs that do not extend asset life are expensed. Software as a service and cloud computing costs are also expensed as incurred due to a lack of legal rights or probable future benefits. Amortization is calculated using the straight-line method over estimated useful lives, with annual reviews for updates.
Perpetualsoftware licenses 5 years Intangible assets are retired when they are fully amortized and derecognized when no future benefits are expected to arise from their use. Any gain or loss on derecognition is recognized in the Statement...
AI summary The text outlines the accounting treatment for intangible assets, specifically noting that perpetual software licenses with a 5-year term are subject to retirement once fully amortized. It further specifies that these assets are derecognized when they no longer provide future benefits, with any resulting gains or losses being recorded in the Statement of Income.
Subsequent Measurement and Amortization Prepaid expenses are subsequently measured at cost less amounts expensed to profit or loss as the related goods or services are consumed. The prepaid balance is amortised on a systematic basis over t...
AI summary The document outlines the accounting treatment for prepaid expenses, specifying that they are subsequently measured at cost minus the amount expensed as goods or services are consumed. Amortization must occur on a systematic basis over the relevant period, aligning with the expected pattern of economic benefit consumption. Furthermore, the amortization of these expenses is to be recognized within the corresponding expense category in the profit or loss statement, such as administrative expenses or cost of sales.
Subsequent Measurement of Right-of-Use Assets ROU assets are subsequently measured at cost less accumulated depreciation and accumulated impairment losses and adjusted for any remeasurement of the related lease liability. ROU assets are de...
AI summary The text outlines the accounting treatment for the subsequent measurement of Right-of-Use (ROU) assets. ROU assets are measured at cost, less accumulated depreciation and impairment losses, with adjustments for lease liability remeasurements. Depreciation follows a straight-line basis from the commencement date until the end of the lease term or the useful life of the underlying asset, whichever occurs first. If IESO Nova Scotia is reasonably certain to exercise a purchase option, depreciation is calculated over the underlying asset's useful life.
17-Year Analysis Timeline The NPV analysis is conducted over a 17-year period. This timeline comprises two distinct phases: - 1. Phase 2A Implementation (2 years) : The first two years are allocated for the implementation of Phase 2A, duri...
AI summary The document outlines the 17-year timeline used for the Net Present Value (NPV) analysis of a project. This timeline is divided into two stages: a two-year initial phase dedicated to implementing Phase 2A to establish foundational operational control capabilities, followed by a 15-year depreciation period. This second phase is intended to reflect the assets' useful life and the timeframe for amortizing both costs and benefits.
Operating costs - 2.22 In this section, we compare and discuss major operating costs of the benchmarking group. These fall generally into the major categories of salaries and benefits; outside services; facility, equipment, various IT and...
AI summary The text analyzes the operating costs of various Independent System Operators (ISOs) and Transmission System Operators (TSOs) as part of a benchmarking exercise. It identifies key cost drivers including salaries, benefits, outside services, and IT/office expenses. Notably, Transpower's high operating costs are attributed to its dual role as both an ISO and a significant transmission asset owner. The analysis distinguishes between incremental ISO costs, transferred utility costs, and excluded costs such as system service procurement, regulatory fees, and non-recurring transition costs.