Matter: NSPI CI# 33525 - $8,016,435 - Canaan Rd. 43V to Tremont 51V Line
1 passage 1 document

Distribution Planning across all matters →

83335NSPI Response to IRs 4 and 5 1 passage
Preamble p. p. 0
3.00 6.00 3.00 0.50 0.50 Report Date: Project Estimate Column A C D E F SWU EST TOTAL CODE DESCRIPTION HOURS UNITS SWU HRS TRANS-IF1TA Install 138kV T-H(2) (138kV Tangent Structure H-Frame Design) 13.00 TRANS-IF1TB Install 138kV T-H(2-O)DE...

AI summary The document contains a detailed list of tasks and hours associated with various infrastructure projects, including the installation and removal of power line structures, poles, and related components for a 138kV transmission system.

Disclaimer: These summaries were generated by AI from the filings they describe. We take care to make them accurate, but errors are possible - and they aren't advice. Only the filings themselves are the record: if you're relying on something here, confirm it against the source documents or the Nova Scotia Energy Board's own record. Full disclaimer →