NON-CONFIDENTIAL 1 Request IR-1: 2 3 For each distribution line that was included in the 2010 program please provide the 4 following information: 5 6 (a) The length of each line 7 8 (b) The peak demand loading of each line in MVA 9 10 (c)...
AI summary The document requests detailed information about distribution lines included in the 2010 program, including their length, peak demand loading, design capacity prior to upgrades, and potential load transfer to adjacent feeders.
19 Length Peak Demand Loading Load Design Capacity Prior to Upgrade Transferable Load Capacity Location Line (km) (MVA) (MVA) (MVA) Three Mile Plains 79V-403 70 4.4 10.0 4.4 Avon 1V-443 164 4.0 10.0 0.0 Dartmouth East 113H-434 42 12.0 20.0...
AI summary The document presents a table with details about electrical lines, including their length, load demand, and capacity before and after upgrades. The table includes locations such as Three Mile Plains, Avon, and Dartmouth East, along with line identifiers and capacities.
18 Location Line Length of Line Reconductored (km) Load Capacity Following Upgrade (MVA) Transferable Load Capacity Following Upgrade (MVA) Number of New Switches/Other Devices Added to Provide New Interconnection Points Three Mile Plains...
AI summary The table provides details on power line upgrades in Nova Scotia, including locations, line lengths, load capacities, and new switches added to support interconnection points. The data highlights specific upgrades at locations such as Three Mile Plains, Avon, and Dartmouth East.