Topic/Matter Intersection

Topic:"Distribution Planning" in M12686

Matter: Nova Scotia Power Inc. - Community Solar Program – 2025 Report
1 passage 1 document

Distribution Planning across all matters →

N-5NSPI (SNS) RIRs 1-5 1 passage
Section 12 p. p. 2
2 The network upgrades indicated in the table above are for single-phase to three-phase line 3 upgrades, three-phase line extensions, and line reconductoring, as determined to be 4 required in the DSIS. 5

AI summary The text refers to network upgrades outlined in a DSIS, including single-phase to three-phase line upgrades, three-phase line extensions, and line reconductoring.

Disclaimer: These summaries were generated by AI from the filings they describe. We take care to make them accurate, but errors are possible - and they aren't advice. Only the filings themselves are the record: if you're relying on something here, confirm it against the source documents or the Nova Scotia Energy Board's own record. Full disclaimer →