Matter: Nova Scotia Power Inc. - CI C0059483 – 83V L-5017 and L-5046 Rebuild Tap - $1,558,116
9 passages 4 documents

Distribution Planning across all matters →

N-1Application 1 passage
Document No: XXX-XX-XXXX-XXXX p. p. 5
Document No: XXX-XX-XXXX-XXXX Transmission Line Infrastructure Required fields: Estimate Classification Stakeholder Consultation/Engagement/Management Plan Defined (D) NR P D D D Work Breakdown Structure (WBS) Not Applicable (NA) NR Start-...

AI summary The document outlines the status of various transmission line infrastructure components, including stakeholder engagement plans, routing options, technical deliverables, and design specifications. It indicates the progress of each task, such as whether it is defined, preliminary, complete, or not applicable.

N-2NSPI (NSEB) RIR-1 3 passages
Section 5 p. p. 6
(f) Both L-5046 and L-5017 transmission lines operate at a voltage of 69kV. (g) The design work required to refurbish the L-5046 tap and to replace 83V-504 involves updating the designs for the 69 kV Right of Way (ROW) switches. Even thoug...

AI summary The text discusses the voltage level of two transmission lines and the design work required for refurbishing a tap and replacing a component, involving site-specific engineering tasks.

Preamble p. p. 6
2 (i) Please refer to Attachment 1, showing the GIS map with structure location changes at the 3 tap location. The structures at the new 83V-504 switch location will be replaced in the 4 same location as existing structures. This design is...

AI summary The document references a GIS map in Attachment 1 that shows changes to structure locations at three tap locations, specifically mentioning the replacement of structures at the new 83V-504 switch location in the same location as existing structures, with the design currently being finalized.

Line No: L5046 p. p. 6
Line No: L5046 Str Type / Line Insulators GPS GPS Grd Air Insp Str Str# Str# ' Span Insu sulators GPS Access Grd Min Grd Clr GC Status Air Insp Str Field Priority Work OrderID Scheduled Comments Env Notification 3ti # Frm Type Angle Span Т...

AI summary The text presents a table containing details about various line structures and insulators along Forest Hill road, including location data, clearance measurements, work orders, and comments related to infrastructure planning and maintenance.

N-3NSPI (NSEB) RIR 2 to 3 - Redacted 3 passages
The following documents will be provided by NS Power: p. p. 15
The following documents will be provided by NS Power: Document Number Document Name Grounding Standards M205Z-P31 – Sheet 2 Exothermic T Connection: Copperweld M205Z-P35 – Sheet 2 Exothermic Ground Rod Connection: Copperweld M205Z-P36 – Sh...

AI summary NS Power will provide various technical documents related to grounding standards, installation procedures, and physical standards for electrical infrastructure, including exothermic connections and switch installations.

Subject to the availability of the engineering service provider, the following timeline is proposed for this work: p. p. 15
Subject to the availability of the engineering service provider, the following timeline is proposed for this work: Milestone Proposed Date PO Issued 12Feb26 Engineering Kick-off Meeting 19Feb26 30% Package Issued 05Mar26 NS Power Comments...

AI summary A proposed timeline for engineering work is outlined, with key milestones including the issuance of design packages and review meetings with NS Power. After the IFC package is accepted, further design changes may be required to address issues during planning, construction, and to reflect the as-built site conditions.

Section 80 p. p. 15
83V-504 Switch and Structure Replacement CI Number: CI C0059483

AI summary The document references a switch and structure replacement project with CI number CI C0059483, indicating a specific infrastructure-related task within Nova Scotia's regulatory framework.

1011952025 Q4 Capital Reports 2 passages
Note 2: This report has been amended to reflect the new Board approval threshold of $1,000,000, effective October 30, 2019.
50050555 1445000 404 222 H + 5 H + B 5 H + 1 247.556 10 004 705 on the Mersey Hydro system.

AI summary The document includes a line item referencing a matter number 50050555 with various codes and a financial value of 247.556, along with a number 10 004 705 and a reference to the Mersey Hydro system.

2025 ACE Carryover Spending - as of December 31, 2025
2025 ACE Carryover Spending - as of December 31, 2025 Project 2025 ACE Plan 2025 ACE Plan Amount C0043010 2022/2023 Wood Pole Retreatment Program 79,470 656,597 - (79,470) C0031268 AMO Critical Equipment Online Monitoring 34,543 432,380 53...

AI summary The document outlines the 2025 ACE Carryover Spending as of December 31, 2025, detailing various projects under the 2025 ACE Plan, including amounts allocated, actual spending, and variances. It includes infrastructure projects such as Wood Pole Retreatment, Breaker Replacement, and Advanced Metering Infrastructure.

Disclaimer: These summaries were generated by AI from the filings they describe. We take care to make them accurate, but errors are possible - and they aren't advice. Only the filings themselves are the record: if you're relying on something here, confirm it against the source documents or the Nova Scotia Energy Board's own record. Full disclaimer →