HomeDistributionM03086Evidence
Topic/Matter Intersection

Topic:"Distribution" in M03086

Matter: CI# 34622 - P-128.10 - NSPI WO - Upgrade L-8002 - $1,648,189
1 passage 1 document

Distribution across all matters →

N-1Redacted Work Order 4/30/2010 1 passage
NON-CONFIDENTIAL p. p. 1
NON-CONFIDENTIAL 1 Transmission Responses 28 Reasons for engaging contractors versus undertaking work with the Company's workforce 29 include the following: 1 Response IR-T11: (cont'd) 2 3 • The work requirement is intermittent. The contra...

AI summary The document discusses the reasons for engaging contractors instead of using NSPI's workforce for intermittent and specialized work. Key reasons include lower contractor costs, the need for specialized skills, and the flexibility contractors provide for varying work locations and content.

Disclaimer: These summaries were generated by AI from the filings they describe. We take care to make them accurate, but errors are possible - and they aren't advice. Only the filings themselves are the record: if you're relying on something here, confirm it against the source documents or the Nova Scotia Energy Board's own record. Full disclaimer →