Home›Distribution›M12104›Evidence
Topic/Matter Intersection

Topic:"Distribution" in M12104

Matter: Riverport Electric Light Commission Complaint - Power Poles - Martin and Wendy Tanner
9 passages 5 documents

Distribution across all matters →

T-1Notice of Complaint (redacted) 1 passage
How do they want the complaint resolved?
How do they want the complaint resolved? I would like to have the current situation remediated so that we are in a position of safety and meeting the current code.I would suggest that either the appropriate poles be installed to create the...

AI summary The complainant, Martin Tanner, requests that the current unsafe power distribution lines be remediated either by installing appropriate poles or burying the lines. He emphasizes the importance of safety over temporary fixes and references a similar situation in Lunenburg where lines were buried due to safety regulations. Supporting documents, including emails, are attached.

T-3Respondents Submission - Strum Report (redacted) 1 passage
4.03 Clearances to Building
4.03 Clearances to Building Minimum conductor clearances from buildings shall be in accordance with chart V-4M. Where buildings exceed three storeys (or 15 m) in height, a clear space at least 2 m wide shall be left either adjacent to the...

AI summary This section outlines the minimum conductor clearances from buildings, including requirements for multi-storey buildings, clear spaces for fire-fighting ladders, and restrictions on wires and cables rubbing against buildings or other plant.

T-6UTILITY (NSEB) RIR-1 to RIR-7 (redacted) 5 passages
(See Rule 36-110 and Appendix B.)
(See Rule 36-110 and Appendix B.) Minimum separation from ground, m Areas acce ssible to pedes Indoors Outdoors Maximum system voltage\ , kV Light snow Heavy snow area† Areas likely to be travelled by vehicles Not exceeding 15 2.9 3.4 4.0...

AI summary The document provides a table specifying the minimum separation from ground for electrical systems in various conditions, including indoors, outdoors, light snow, heavy snow areas, and areas likely to be travelled by vehicles, based on maximum system voltage.

4.03 Clearances to Building
4.03 Clearances to Building Minimum conductor clearances from buildings shall be in accordance with chart V-4M. Where buildings exceed three storeys (or 15 m) in height, a clear space at least 2 m wide shall be left either adjacent to the...

AI summary This section outlines the minimum conductor clearances required from buildings, including specific requirements for taller buildings and the prohibition of wires rubbing against buildings. It emphasizes the need for clear spaces to allow ladder access for firefighting and applies to all parts of a building, including fixtures and communication cables.

Section 19
COLUMN 2: CONDUCTOR SWING BASED ON 75 m NON-SHELTERED SPAN. COLUMN 3: DESIGN HORIZONTAL CLEARANCE - TOTAL OF COLUMNS I AND 2. - 'A. THE VERTICAL CLEARANCES APPLY UNDER CONDITIONS OF MAXIMUM SAG. B. THE HORIZONTAL CLEARANCES ARE FROM THE IN...

AI summary The text outlines specific conductor swing and clearance requirements for electrical installations, including vertical and horizontal clearances based on span length, building type, and voltage levels. It also references applicable codes and standards for 7.2kV rms open/bare conductors.

Clearance Distance Reference Per CSA Standard C22.3 No. 1:20, "Overhead Systems" Per CSA Standard C22.1:21, "Canadian Electrical Code (25th Edition)" Per Nova Scotia Power Inc., "Overhead Dist
Clearance Distance Reference Per CSA Standard C22.3 No. 1:20, "Overhead Systems" Per CSA Standard C22.1:21, "Canadian Electrical Code (25th Edition)" Per Nova Scotia Power Inc., "Overhead Distribution Standard" Minimum Horizontal Clearance...

AI summary The document compares minimum clearance distances for overhead power lines from buildings and ground, referencing CSA standards and Nova Scotia Power Inc. standards. Horizontal and vertical clearance requirements are outlined, with measurements provided in both meters and feet.

3. Field Measurements and Remedial Work:
3. Field Measurements and Remedial Work: With the assistance of the Riverport Electric Light Commission (RELC) the original horizontal and vertical clearance distances were measured from the Tanner Residence to the RELC 7.2kV, single phase...

AI summary This section discusses field measurements and remedial work conducted with the assistance of the Riverport Electric Light Commission (RELC) to determine the original horizontal and vertical clearance distances from the Tanner Residence to the RELC 7.2kV, single phase open/bare conductor.

99194Board Decision Letter - Redacted 1 passage
BACKGROUND
BACKGROUND You are a customer of RELC. In your complaint, you stated that you purchased the property located at , in August 2024. While working on the property, you noticed that the RELC's electrical distribution lines are situated in clos...

AI summary A customer of RELC raised concerns about the proximity of electrical distribution lines to their property, citing potential safety risks. RELC responded that there are no Board-approved regulations on minimum clearance distances and that a third-party engineering report found no compliance issues. RELC also noted that the deck was likely built after the lines were installed.

99194Board Decision Letter - Redacted 1 passage
BACKGROUND
the deck to those distribution lines and equipment is likely a result of subsequent construction and so should not require changes to the pre-existing configuration in any event. [Exhibit T-2, p. 2] RELC did not initially provide the Strum...

AI summary The document discusses the lack of clearance measurements by Strum Engineering, reliance on RELC and Google Earth data, and a response from the utility regarding property modifications and distribution line clearance requirements.

Disclaimer: These summaries were generated by AI from the filings they describe. We take care to make them accurate, but errors are possible - and they aren't advice. Only the filings themselves are the record: if you're relying on something here, confirm it against the source documents or the Nova Scotia Energy Board's own record. Full disclaimer →