Matter: Nova Scotia Power Inc. - CI C0061550 – L5031 Replacements and Upgrades – Hubbards to East Chester - $6,957,058 (ATO)
4 passages 4 documents

Distribution across all matters →

N-2NSPI (NSEB) RIRs 1-10 - Redacted 1 passage
CI C0061550 – L5031 Replacements and Upgrades – Hubbards to East Chester (NSEB M12961) NSPI Responses to NSEB Information Requests
CI C0061550 – L5031 Replacements and Upgrades – Hubbards to East Chester (NSEB M12961) NSPI Responses to NSEB Information Requests 1 Request IR-4: L5031-074 2Pole: 69- Tangent 189 10 40 40 1/0 No Suspensio 15 Porcelain -64 12' 44 36' in ti...

AI summary The document contains a table with detailed information about infrastructure upgrades and replacements for L5031 lines from Hubbards to East Chester. It includes data on poles, structures, materials, locations, and conditions of the infrastructure, as well as some notes on failures and repairs.

N-4NSPI (NSEB) RIR 19 to 24 1 passage
CI C0061550 NSEB IR-20 Attachment 1 Page 1 of 1
CI C0061550 NSEB IR-20 Attachment 1 Page 1 of 1 Mobile Year Installation Date Removal Date Location Reason for Mobile Transformer Number Transformer Rating Voltage Level Number of Customers Affected 5P 2025 January February L-5031 Transmis...

AI summary NS Power uses a prioritization strategy based on system reliability risk, geographic coverage, and technical compatibility when deploying mobile transformers, particularly during shortages. The approach emphasizes maintaining system resilience and flexibility for emergency responses.

103363NSEB (NSPI) IR 11 to 18 1 passage
Request IR-12:
Request IR-12: In response to IR-2, NS Power states: The mobile transformer unit was initially installed at the Robinsons Corner location, at the intersection of L-5031-113 and L-5031A-030A. - a) Please describe the connection of the mobil...

AI summary NS Power is requested to provide detailed information on the installation and operation of a mobile transformer unit and three bypass structures, including diagrams, GIS maps, and explanations of their connections, purposes, and associated feeders and service areas.

103604NSEB (NSPI) IR 19 to 24 1 passage
Request IR-21:
Request IR-21: - Please describe how NS Power determines when to use a mobile transformer and the criteria or - strategies used to prioritize locations when there is a shortage of available mobile transformers, - as in the current case.

AI summary The request asks NS Power to explain how it decides when to use a mobile transformer and the criteria used to prioritize locations during shortages, such as the current situation.

Disclaimer: These summaries were generated by AI from the filings they describe. We take care to make them accurate, but errors are possible - and they aren't advice. Only the filings themselves are the record: if you're relying on something here, confirm it against the source documents or the Nova Scotia Energy Board's own record. Full disclaimer →