E-12023 DSM Annual Progress Repot 1 passage
DEMAND RESPONSE (2023) p. p. 35
DEMAND RESPONSE (2023) - E1's supplier provided a proposal outlining replacement controller technologies in Q4. The selection of the replacement controller is expected to be completed early 2024, following testing of the new units (four te...

AI summary E1's supplier proposed replacement controller technologies for testing in Q1 2024, with installations starting in Q2 2024. Removal of DLC controllers will prevent meeting the 2024 Residential Demand Response capacity target, though BNI pathways will offset this. The Eco Shift pilot, launched in December 2023 with NS Power, has enrolled 934 thermostats and 9 EV chargers, with batteries expected in Q2 2024.

Disclaimer: These summaries were generated by AI from the filings they describe. We take care to make them accurate, but errors are possible - and they aren't advice. Only the filings themselves are the record: if you're relying on something here, confirm it against the source documents or the Nova Scotia Energy Board's own record. Full disclaimer →