Topic/Matter Intersection

Topic:"Efficiency Preferred Partner" in M12030

Matter: EfficiencyOne (EOne) for approval of a Supply Agreement – Behavioral Program Update
1 passage 1 document

Efficiency Preferred Partner across all matters →

E-2EOne (NSUARB) - RIR -1 to 5 1 passage
1 Request IR-02: p. p. 0
1 (b) This unexpected limitation was identified as E1 and NS Power worked through the details 2 of the evaluation approach as proposed in the April 8, 2024 letter. The data that is available 3 from the existing NS Power CEM evaluation is n...

AI summary The document discusses a revised agreement between EOne and NS Power regarding energy savings evaluation, with the NSUARB requiring third-party verification. It also addresses reporting requirements and confirms they will not change.

Disclaimer: These summaries were generated by AI from the filings they describe. We take care to make them accurate, but errors are possible - and they aren't advice. Only the filings themselves are the record: if you're relying on something here, confirm it against the source documents or the Nova Scotia Energy Board's own record. Full disclaimer →