E-25Evidence of A. Napoleon and K. Takahashi, on behalf of BCC Synapse 1 passage
Preamble p. p. 13
- 10 All values are levelized, except the cost of gas. - 11 Consistent with the IRP, all values are in CAD 2019$. We adjusted values using a 2% inflation 12 rate and an exchange rate of $1.31 CAD per $1.00 USD (consistent with the IRP). -...

AI summary The document discusses the calculation of levelized costs for energy generation, particularly for Gas Combined Cycle (Gas CC) plants, using data from the Integrated Resource Plan (IRP) and other sources such as the National Renewable Energy Laboratory and the U.S. EIA Annual Energy Outlook. It outlines methods for adjusting costs for inflation and exchange rates, and mentions the extrapolation of wind and solar costs.

Disclaimer: These summaries were generated by AI from the filings they describe. We take care to make them accurate, but errors are possible - and they aren't advice. Only the filings themselves are the record: if you're relying on something here, confirm it against the source documents or the Nova Scotia Energy Board's own record. Full disclaimer →