102167NSEB (BEC) IR-1 to IR-42 1 passage
Request IR-26:
Request IR-26: On page 86 of Condition Assessment, Section 6.1.1, Hysovent noted the lack of studies and records needed to develop an accurate flow estimate, as quoted below: Unfortunately, for the Factorydale reservoir, we don't have a hy...

AI summary The text raises questions about the accuracy of flow estimates for the Factorydale reservoir, which rely on extrapolated data from the Kelley River. It asks BEC to clarify how the design flow of 3.39 m3/s was determined, the data sources used, and whether hydrology studies were conducted to validate the proposed generation capacity increase.

Disclaimer: These summaries were generated by AI from the filings they describe. We take care to make them accurate, but errors are possible - and they aren't advice. Only the filings themselves are the record: if you're relying on something here, confirm it against the source documents or the Nova Scotia Energy Board's own record. Full disclaimer →