I. SUMMARY NERC herein submits proposed Rules of Procedure revisions that add two new functional entities to the NERC registry criteria – Computational Load Owner and Computational Load Operator. Through this proposal, NERC takes steps to...
AI summary NERC is proposing revisions to its Rules of Procedure to introduce two new functional entities to its registry: Computational Load Owner and Computational Load Operator. This initiative aims to mitigate reliability risks posed by the rapid growth of large computational loads, such as data centers and large industrial facilities, on the Bulk Power System (BPS). The proposal is based on findings from NERC's Long-Term Reliability Assessments (LTRAs), which identified these large loads as significant emerging risks to grid stability.
A. NERC Large Loads Action Plan Over the past few years, NERC in its Long-Term Reliability Assessments identified unprecedented load growth, noting that demand growth is higher than at any point in the last two decades. 21 This projected i...
AI summary The text discusses the North American Electric Reliability Corporation (NERC) Large Loads Action Plan, which addresses unprecedented electricity demand growth in North America. This growth is primarily driven by the digital economy, specifically data centers for artificial intelligence. The rapid expansion of these large loads presents unique challenges for demand forecasting and system behavior planning. NERC is collaborating with stakeholders to ensure transmission system reliability and mitigate potential impacts on the Bulk Power System (BPS).
1. NERC Large Loads Working Group As part of the NERC Large Loads Action Plan, NERC engaged the Reliability and Security Technical Committee Large Loads Working Group ("LLWG") 24 to assess the risks to the reliability of the BPS posed by l...
AI summary The text describes the activities of the NERC Large Loads Working Group (LLWG), which was established to assess risks to the Bulk Power System (BPS) posed by large loads. NERC identified specific risks associated with emerging power electronic loads, such as those for data centers, artificial intelligence, and cryptocurrencies. These loads are characterized by high energy consumption, variable demand, significant cooling requirements, and the use of software controls to manage load behavior, which differ from traditional electrical characteristics.
r. 17, 2026), responding entities reported they could not gather modeling information or did not have direct coordination with large load entities, corroborating the gaps identified in Whitepaper #2. While the work under the Large Loads Ac...
AI summary The text discusses NERC incident reviews highlighting reliability risks associated with the growth of computational loads, specifically data centers and crypto-mining facilities. Two specific incidents are cited: a 2024 disturbance in the Eastern Interconnection where 1,500 MW of voltage-sensitive data center load was lost simultaneously, and load-loss events in the ERCOT Interconnection caused by the unique ride-through characteristics of crypto-mining facilities. NERC warns that increasing computational load poses growing risks to frequency and voltage stability.
3. Need for New Functional Entities The severity of the aggregate risk posed by the types of occurrences outlined in the incident reviews grows with the amount of computational load expected on the system. In the Level 2 Alert report, NERC...
AI summary The text discusses the increasing reliability risks posed by the proliferation of large computational loads on the Bulk Power System (BPS). NERC identifies that computational loads may account for 90% of large loads by 2027, presenting unique electrical behaviors and geographic concentrations that threaten grid stability. To mitigate these risks, NERC is proposing new registry criteria and Reliability Standards to help grid planners understand load profiles. Interim measures include Level 3 Essential Action Alerts and Reliability Guidelines to manage load reductions and oscillations.
Accordingly, NERC initially considered a 20 MW and 60 kV threshold would include a majority of entities contributing to the reliability risk posed by the connection of computational loads to the BPS. After further analysis and consideratio...
AI summary The text discusses North American Electric Reliability Corporation (NERC) deliberations regarding the threshold for including computational loads in reliability risk assessments. NERC proposed a 50 MW and 100 kV threshold, balancing the inclusion of significant computational load while excluding smaller entities. Data analysis indicates approximately 79,502 MW of data center load will be active by the end of 2027, with most entities at or above the 50 MW threshold likely connecting at 100 kV or higher due to physical and reliability constraints.