Matter: P-194 - NSPI - 10 Year System Outlook 2010-2019 - June 30, 2010
1 passage 1 document

Emergency Response across all matters →

N-110 Year System Outlook 2010-2010 Report dated June 30, 2010 6/30/2010 1 passage
Export Import p. p. 20
Export Import Number of thermal units armed for NS system load level (Import less than generation rejection (maximum two) 22% of total system load) Reactive Power Support level in the Halifax Regional Municipality Percentage of dispatchabl...

AI summary The document discusses the potential risks to the NSPI system if it becomes separated from New Brunswick during export, leading to increased system frequency. To mitigate this, NSPI employs fast-acting Special Protection Systems to reject generation and stabilize the system.

Disclaimer: These summaries were generated by AI from the filings they describe. We take care to make them accurate, but errors are possible - and they aren't advice. Only the filings themselves are the record: if you're relying on something here, confirm it against the source documents or the Nova Scotia Energy Board's own record. Full disclaimer →