24. FORCE MAJEuRE - 24.1 The Parties shall not be in default or in breach of this Agreement due to any delay or failure to meet any of their obligations caused by or arising from any event beyond their reasonable control and without their...
AI summary The force majeure clause outlines that parties are not in default for obligations unmet due to events beyond their control. Canada's liability is limited to its proportional incentive share until the event occurs. Performance delays are permitted for the duration of the event, with termination allowed after one year. Affected parties must notify the other and provide evidence of the force majeure event.
Emergency Condition shall mean a condition or situation: - (1) that in the judgment of the Party making the claim is imminently likely to endanger life or property; or - (2) that, in the case of a Transmission Provider, is imminently likel...
AI summary The text defines 'Emergency Condition' as situations endangering life/property or causing material harm to transmission systems or generating facilities. It also outlines 'Energy Resource Interconnection Service' and 'Engineering & Procurement (E&P) Agreement' related to interconnection processes and transmission provider obligations.
9.11 Emergency Numbers Each Party will provide, by written notice, an emergency telephone number, staffed 24 hours a day, to call in case of an emergency. Beginning of the Effective Date of this Agreement, and until modified in writing: Th...
AI summary Section 9.11 requires each party to provide a 24/7 emergency telephone number. The Transmission Provider's number is 902-428-7739, and the Interconnection Customer's number is 902-474-7828, effective from the Agreement's Effective Date unless modified in writing.
11.6.1 Interconnection Customer Compensation for Actions During Emergency Condition Transmission Provider or RTO or ISO shall compensate Interconnection Customer for its provision of real and reactive power and other Emergency Condition se...
AI summary The Transmission Provider, RTO, or ISO must compensate the Interconnection Customer for providing real and reactive power and other emergency services during an Emergency Condition, as outlined in Article 11.6. This ensures fair remuneration for support provided to the Transmission System during critical periods.
ARTICLE 13. EMERGENCIES
AI summary The document section titled 'ARTICLE 13. EMERGENCIES' outlines procedures for handling emergencies but contains no substantive content or specific details in the provided text.
13.3 Notice Transmission Provider shall notify Interconnection Customer promptly when it becomes aware of an Emergency Condition that affects the Transmission Provider's Interconnection Facilities or the Transmission System that may reason...
AI summary Section 13.3 outlines mutual obligations for Transmission Providers and Interconnection Customers to notify each other of Emergency Conditions affecting facilities or the Transmission System. Notifications must detail the emergency, its impact, duration, and corrective actions, with a follow-up written notice required.
13.4 Immediate Action Unless, in Interconnection Customer's reasonable judgment, immediate action is required, Interconnection Customer shall obtain the consent of Transmission Provider, such consent to not be unreasonably withheld, prior...
AI summary The section outlines procedures for manual switching operations during emergencies at generating facilities or interconnection customer facilities. Consent from the transmission provider is required unless immediate action is deemed necessary by the interconnection customer, with consent not to be unreasonably withheld.
13.5.1 General Transmission Provider may take wh~tever actions or inactions with regard to the Transmission System or the Transmission Provider's Interconnection Facilities it deems necessary during an Emergency Condition in order to - (i)...
AI summary The Transmission Provider may take actions during emergencies to ensure public safety, system reliability, and service restoration. It must minimize impacts on generating facilities and may require them to adjust operations, including power output changes or shutdowns, while complying with technical and legal standards.
13.5.2 Reduction and Disconnection Transmission Provider may reduce Interconnection Service or disconnect the , Generating Facility or the Interconnection Customer Interconnection Facilities, when such, reduction or disconnection is necess...
AI summary The Transmission Provider may reduce or disconnect interconnection services during emergencies under Good Utility Practice, distinct from curtailment rights in the Tariff. Advance notice and coordination with the Interconnection Customer are required, with restoration to normal operations prioritized post-emergency.