NON-CONFIDENTIAL 1 Request IR-4: 2 3 Please elaborate on the estimated load and the maximum contingency capacity of the 4 Kempt Road substation for the 2010/11 and 2011/12 winter peaks. 5 6 Response IR-4: 7 8 The load and contingency capac...
AI summary NSPI responds to a request for details on Kempt Road substation's 2010/11 and 2011/12 winter peak load and contingency capacity, stating minimal differences between the two periods made data aggregation unnecessary. Transformer loads for three Halifax Peninsula substations are provided in MVA.