Matter: Nova Scotia Power Inc. - CI C0061550 – L5031 Replacements and Upgrades – Hubbards to East Chester - $6,957,058 (ATO)
1 passage 1 document

Emergency Response across all matters →

103363NSEB (NSPI) IR 11 to 18 1 passage
Request IR-13:
Request IR-13: In response to IR-5 a), NS Power states: NS Power owns three 25 MVA mobile transformers. To ensure emergency preparedness across the system, at least one 25 MVA mobile transformer must remain available for deployment and sho...

AI summary NS Power is responding to a request regarding the use of mobile transformers for emergency preparedness and project timelines. The transformer deployment on L-5031 was removed to ensure availability for emergency use, and the L5031 Replacements and Upgrades project has faced delays due to transmission line outage restrictions.

Disclaimer: These summaries were generated by AI from the filings they describe. We take care to make them accurate, but errors are possible - and they aren't advice. Only the filings themselves are the record: if you're relying on something here, confirm it against the source documents or the Nova Scotia Energy Board's own record. Full disclaimer →