is expected to decrease over time as the additional renewable resources displace coal-fired generation. However, the unit is estimated to continue generating approximately 230.8 GWh of energy in 2028. Based on the evidence filed in this pr...
AI summary The Board approves the TRE5 IP-LP Turbine Refurbishment project, citing the necessity of maintaining reliable energy supply in Nova Scotia. The project is deemed essential for ensuring safe, secure, and economical energy provision, in line with the Energy and Regulatory Boards Act. The project's costs are supported and approved at $2,963,160.