Why do this project this way? A third-party engineering assessment outlined that the performance issues in removing the stoplogs observed in sluiceway Bays 1 and 6 may be the result of the following, or a combination thereof: - a. Deformat...
AI summary The project involves addressing performance issues in sluiceway Bays 1 and 6 by lowering the water level in Lower Great Brook headpond to 108 ft to safely remove and replace stoplogs. A third-party assessment identified structural deformation and construction discrepancies as potential causes. NS Power obtained a Fisheries Act Authorization to facilitate the drawdown and refurbishments.