Year PHP Load (GWh) ADC Load Shifting Differential ($M) Benefit to Other Customers ($M) 2020 875 6.6 7.3 2021 966 (16.7) 3.9 2022 957 (48.9) 3.8 2023 670 (33.6) 2.7 2024 766 (0.8) 3.1 2025 691 1.5 4.4 In response to Recommendation XIV-1 in...
AI summary The table presents annual data on PHP Load (GWh), ADC Load Shifting Differential ($M), and Benefit to Other Customers ($M) from 2020 to 2025. The data shows fluctuating values, with a notable negative differential in 2021 and 2022. The text references a recommendation from the 2020-2021 FAM Audit Report (M10416) and indicates additional context will be provided.
For the Year Ended December 31, 2025 YTD Dec $ YTD Dec MWh ELIADC in Annual FAM Report (reported on A3) $ 64,738,555 690,763 2025 ADC Adjustment (1) $ 11,022 2024 ADC Adjustment (2) $ (1,221,077) 2024 VOM Adjustment (2) $ 52,067 Power Fact...
AI summary The document provides a summary of financial and operational data for the year ended December 31, 2025, including ELIADC in the Annual FAM Report, ADC and VOM adjustments, and CBL Energy Charge details. It includes a table with data for January 2025, covering fuel and purchased power charges, operating and maintenance charges, and various adjustments and benefits.
Cause Code 2 - NDN - NSP Energy System Operator initiated ramp Down Total Billed $ 100.85 Cause Code 3 - PFL - PHP Failure to Load due to equipment or process constraints ADC $ (2.20) Cause Code 4 - PNA - PHP and NSP Agreement to new dispa...
AI summary This text details various cause codes related to energy system adjustments and billing, including ramp down events, failure to load due to equipment constraints, and adjustments related to the Active Demand Control (ADC) program. It also provides information on the total cost to serve PHP in 2025.