4. Guidance on the most practical, reasonable and financially conscious options available for upgrading to 200A service, whether overhead or underground [Applicant's Letter, November 24, 2025, p. 7] In response to Board Information Request...
AI summary NS Power explains that upgrading to a 200A service must comply with the Canadian Electrical Code and internal regulations, with the customer responsible for upgrades from the URD box to the service entrance and NS Power responsible up to the URD box. The underground service upgrade is a shared expense.