Topic/Matter Intersection

Topic:"Energy Efficiency Portfolio Standard Eeps" in M12551

Matter: Nova Scotia Power Inc. - 2026 Annually Adjusted Rates (AARs)
2 passages 2 documents

Energy Efficiency Portfolio Standard Eeps across all matters →

N-1Application - Redacted 1 passage
SPECIAL CONDITIONS p. p. 176
SPECIAL CONDITIONS - (1) The Port Authority owns and is responsible for the maintenance and operation of all electrical equipment required for the supply of port electricity to docked ships other than the meters and metering transformers s...

AI summary The document outlines special conditions for electricity supply to ships at the port, including responsibilities for equipment maintenance, metering arrangements, and power factor requirements. The Port Authority and NSPI have defined roles, and customers may be required to contribute to capital costs for special metering.

N-6NSPI (REI) RIR 1 to 20 - Redacted 1 passage
Annually Adjusted Rates for 2026 (M12551) NSPI Responses to REI Information Requests p. p. 63
Annually Adjusted Rates for 2026 (M12551) NSPI Responses to REI Information Requests 1 Request IR-2: 22 cost is highly dependent on the timing of the pricing, which varies according to seasonal, 23 daily, and hourly market fluctuations. Ty...

AI summary NSPI discusses the cost of HFO generation at Tuft's Cove, noting its high cost relative to natural gas and seasonal market fluctuations. The company also mentions limited access to 2025 AAR forecasts due to a cyber event, with actual solid fuel plant hours exceeding forecasts by 12%.

Disclaimer: These summaries were generated by AI from the filings they describe. We take care to make them accurate, but errors are possible - and they aren't advice. Only the filings themselves are the record: if you're relying on something here, confirm it against the source documents or the Nova Scotia Energy Board's own record. Full disclaimer →