1. Scope of Evergreen IRP 2022 Update – Assumptions AREA and the MEUs agree that changes have occurred since 2020 that warrant significant modeling updates. On Slide 2 of the 2022 Evergreen IRP Study Scope, NS Power states that the "evergr...
AI summary AREA and MEUs emphasize the need for updated assumptions in the Evergreen IRP 2022 study, requiring stakeholder input on GHG compliance modeling, Net Zero 2035 targets, firm import capacity, interconnection projects (TSR 411/412), battery storage, wind integration, and coal conversions. They stress transparency and timely information sharing to ensure assumptions reflect current data.
Attachment 2 NS Power Responses to Stakeholder Comments Theme Stakeholder Comment NS Power Response 1. Refresh input assumptions on an expedited schedule. We understand that finalizing some inputs may require more complex steps and be sens...
AI summary Stakeholders requested expedited updates to input assumptions and single-scenario modeling for the IRP. NS Power responded by incorporating early modeling insights into the evergreen IRP schedule, including draft assumptions and scenarios for stakeholder review.