Date Filed: August 22, 2025 NSPI (NSEB) IR-4 Page 1 of 1 1 Request IR-5: 2 3 Reference to 2025 10-Year System Outlook (M12386), page 17 of 64 (Figure 7), NS Power 4 notes that Point Aconi will be retired on 2029/2030. 5 6 (a) How does the...
AI summary The document outlines a request for information regarding NS Power's boiler refurbishment at Point Aconi Generating Station and its alignment with the 80% renewable energy generation goal by 2030. NS Power responds that the refurbishment ensures safe and reliable operation through the station's planned retirement in 2029/2030, supporting system reliability during the energy transition.