1 Request IR-1: 2 3 The report states that actual measurements were unavailable for the Metro region and 4 forecast values from December 19, 2025, at 04:00 were used instead. Please explain: 5 6 (a) Why actual Metro observations were unava...
AI summary The text discusses the unavailability of actual measurements for the Metro region and the use of forecast values in a report, along with the explanation that the missing data was due to a data stream issue from Environment Canada. It also outlines the methodology NS Power uses for storm event cause assignments.