KEY QUESTIONS In the NSEB's order for IESO Nova Scotia's Approval of its Proposed Expenditure and Revenue Requirement for the Test Year Ending March 31, 2026 (M12412), the following direction was provided for this IRP: "IESO Nova Scotia is...
AI summary The NSEB directed IESO Nova Scotia to address specific issues in its Integrated Resource Plan (IRP), including analyzing new resource costs, regional system approaches, and emissions-linked modeling. Three additional key questions focus on decarbonization targets, offshore wind opportunities, and Mersey Hydro redevelopment.