NON-CONFIDENTIAL
p. p. 0
NON-CONFIDENTIAL 1 Request IR-1: 2 3 On page 4 of 20, under "Why do this project now?", NSPI states this project is being 4 advanced at this time to reduce the probability of loss of load due to a transformer failure. 5 Please provide spec...
AI summary NSPI justifies submitting a transformer replacement project as a U&U work order rather than part of the 2011 ACE Plan, citing a 2010 failure of two Kempt Road substation transformers, leaving only one aging unit operational. The project aims to prevent potential load loss if the remaining transformer fails.