HomeEnergy EfficiencyM03718Evidence
Topic/Matter Intersection

Topic:"Energy Efficiency" in M03718

Matter: CI# 33562 - P-128.10 - NSPI WO - FAC Land Registration Act - $1,899,162ACE Amount ($1,892,331) - $52K spent to date
3 passages 3 documents

Energy Efficiency across all matters →

06458Board Decision Letter 2/24/2011 1 passage
Section 1 p. p. 0
Nova Scotia Utility and Review Board Mailing address PO Box 1692, Unit"M" Halifax, Nova Scotia B3J 3S3 [email protected] Web www.nsuarb.ca Office 3rd Floor 1601 Lower Water Street Halifax, Nova Scotia 83J 3P6 902424-4448 t 902424-3919 f...

AI summary Nova Scotia Power Inc. (NSPI) requested approval for a $1,899,162 2010 ACE Plan Work Order to migrate 612 property titles to a new land registration system. The Nova Scotia Utility and Review Board reviewed the application, accepted confidential portions, and approved the request, deeming the project necessary and costs justified.

06001Information Requests 1 passage
NOVA SCOTIA UTILITY AND REVIEW BOARD
NOVA SCOTIA UTILITY AND REVIEW BOARD IN THE MATTER OF: THE PUBLIC UTILITIES ACT - and- IN THE MATTER OF: AN APPLICATION by Nova Scotia Power Incorporated ("NSPI") for Approval of 2010 ACE Plan Work Order Greater Than $1 Million: CI# 33562...

AI summary Nova Scotia Power Inc. (NSPI) seeks approval for a 2010 ACE Plan Work Order exceeding $1 million under the Land Registration Act. The Nova Scotia Utility and Review Board requests details on project timelines, property migration numbers, and $17,000 in incurred costs. Responses are due January 7, 2011.

06458Board Decision Letter 2/24/2011 1 passage
Section 1 p. p. 0
Nova Scotia Utility and Review Board Mailing address PO Box 1692, Unit"M" Halifax, Nova Scotia B3J 3S3 [email protected] Web www.nsuarb.ca Office 3rd Floor 1601 Lower Water Street Halifax, Nova Scotia 83J 3P6 902424-4448 t 902424-3919 f...

AI summary Nova Scotia Power Inc. (NSPI) requested approval for a $1.899 million Work Order under the 2010 ACE Plan to migrate 612 property titles to a new land registration system. The Nova Scotia Utility and Review Board reviewed the application, accepted confidential portions, and approved the request, deeming the project necessary and costs justified.

Disclaimer: These summaries were generated by AI from the filings they describe. We take care to make them accurate, but errors are possible - and they aren't advice. Only the filings themselves are the record: if you're relying on something here, confirm it against the source documents or the Nova Scotia Energy Board's own record. Full disclaimer →