HomeEnergy EfficiencyM12247Evidence
Topic/Matter Intersection

Topic:"Energy Efficiency" in M12247

Matter: Nova Scotia Power Inc. - Evergreen IRP Action Plan & Roadmap Update
3 passages 3 documents

Energy Efficiency across all matters →

N-1Integrated Resource Plan Action Plan Update 2025 1 passage
Hybrid Peak Electrification Scenario Action Item 4b p. pp. 39-40
Hybrid Peak Electrification Scenario Action Item 4b - As part of the electrification study, a hybrid heating electrification profile was assessed: - o Represents the peak load reduction associated with retaining back up heating sources (na...

AI summary A hybrid peak electrification scenario was assessed as part of the Evergreen Integrated Resource Plan (IRP), demonstrating value in reducing system costs and resource capacity requirements. NS Power is committed to participating in further studies led by Net Zero Atlantic to assess the cost and benefits of the hybrid approach, with work continuing into 2025.

N-4NSPI (IG) RIR 1 to 10 1 passage
IR SIS Status COD p. p. 5
[nspi-combined-interconnection-request-queue(pdf).pdf](https://www.nspower.ca/docs/default-source/pdf-to-upload/nspi-combined-interconnection-request-queue(pdf).pdf?sfvrsn=d56d149_88) IR SIS Status COD 18 export offtake opportunities are s...

AI summary The text discusses the development of renewable hydrogen and related initiatives, including the 2025 H2Global auction, and outlines pending actions related to tariff applications and power purchase agreements. It also raises questions about feasibility studies for a new clean technology by HyVera.

N-7NSPI (SBA) RIR 1 to 18 1 passage
NON-CONFIDENTIAL p. p. 12
NON-CONFIDENTIAL 1 Request IR-4: 29 Power and the forecast cost of providing these services over the coming decades). 1 • The development of a tariff construct under which these services would be provided 2 by NS Power. 3 4 • The engagemen...

AI summary The document discusses the development of a tariff construct for hydrogen and ammonia production services by NS Power, noting that engagement with developers has included tariff design and analysis, which remains under development and subject to change as project plans and export markets evolve.

Disclaimer: These summaries were generated by AI from the filings they describe. We take care to make them accurate, but errors are possible - and they aren't advice. Only the filings themselves are the record: if you're relying on something here, confirm it against the source documents or the Nova Scotia Energy Board's own record. Full disclaimer →