Home›Energy Efficiency›M12273›Evidence
Topic/Matter Intersection

Topic:"Energy Efficiency" in M12273

Matter: Board Inquiry into Nova Scotia Power's Cybersecurity Incident
5 passages 5 documents

Energy Efficiency across all matters →

N-1Letters of Comment - Redacted 1 passage
Section 105
Sincerely, Weldon Young From: Painting-MacLean, Kimberly To: Painting-MacLean, Kimberly Subject: M12273 FW: NS power Date: November 28, 2025 1:21:01 PM From: Jessica Bradstock-Young Sent: November 19, 2025 12:41 PM To: Fisher, Darren - M.P...

AI summary The email expresses frustration with NS Power, citing concerns about lack of accountability, transparency, and privacy breaches, as well as the installation of smart meters that may pose safety risks. The sender requests a full audit and criticizes the company for hiding information about its leadership.

102372NSPI Monthly Update Report #9 1 passage
The following projects experienced adjustments to their completion timeline. An overview of the changes and associated rationale is outlined below: p. p. 6
The following projects experienced adjustments to their completion timeline. An overview of the changes and associated rationale is outlined below: Pillar Project Summary of Change Rationale Customer Energy Management (CEM) Evaluation, Mea...

AI summary The document outlines timeline adjustments for projects under the Customer Energy Management (CEM) and Evaluation, Measurement, and Verification (EM&V) pillars. The 2025 CEM EM&V is in progress and planned for filing on or before July 1, 2026, with the restoration of My Energy Insights (MEI) systems expected by the end of Q3 2026. The rationale for the changes includes project progress and completion timelines.

103204NSPI Monthly Update Report #11 1 passage
Additional Capabilities
Additional Capabilities Progress continued across the remaining portfolio of restoration activities, with additional solutions moving into steady-state operations. During the reporting period, the Energy and Marketing restoration initiativ...

AI summary The document discusses the progress of restoration activities, including the completion of the Energy and Marketing restoration initiative, which is now in operational service. Focus has shifted to normal operations, user enablement, and ongoing management, with other initiatives advancing through testing and deployment aligned with business priorities.

103622NSPI Monthly Update Report #12 1 passage
The following projects experienced adjustments to their completion timeline. An overview of the changes and associated rationale is outlined below:
The following projects experienced adjustments to their completion timeline. An overview of the changes and associated rationale is outlined below: Pillar Project Summary of Change Rationale E1's Residential Behaviour Program Introduced NA...

AI summary Several projects have experienced timeline adjustments, including E1's Residential Behaviour Program, which will not resume in 2026 due to the need for a minimum of one bill cycle following data reintroduction into MEI. The MEI platform is expected to be available by the end of Q4 2026. Other projects, such as the Joint Use Agreement Proceeding and Customer Energy Management EMAV, are also undergoing changes with updates expected in Q1 2027 and Q3-Q4 2026, respectively.

103914NSPI Monthly Update Report #13 1 passage
Incident Impact and Response
Incident Impact and Response Recovery work continued to progress during the reporting period, with stable operations maintained while efforts remained focused on governance, process improvements, and completion of the remaining recovery ac...

AI summary Recovery work continued during the reporting period with stable operations maintained. Efforts focused on governance, process improvements, and completing remaining recovery activities, supporting resilience, efficiency, and service delivery improvements.

Disclaimer: These summaries were generated by AI from the filings they describe. We take care to make them accurate, but errors are possible - and they aren't advice. Only the filings themselves are the record: if you're relying on something here, confirm it against the source documents or the Nova Scotia Energy Board's own record. Full disclaimer →