16 Exhibit N-3, Midgard Evidence, February 18, 2026, page 39, lines 4-5. 1 SM Electrician 2 Install RTU hardware and power up RTU o 3 Install wiring for RTU and field devices o 4 5 Engineering 6 Prepare SCADA drawings o 7 Update existi...
AI summary The text discusses the technical complexity and sequential nature of RTU replacement, arguing that Midgard's recommendation for a 30% reduction in installation time is not technically supportable due to underestimation of duration, site-specific complexity, and misallocation of travel time and engineering requirements.