Matter: Nova Scotia Power Inc. - CI C0053699 – Renewable to Retail Implementation - $5,644,468
3 passages 2 documents

Energy Management Information Systems across all matters →

N-3NSPI (NSEB) RIR 1 to 15 - Redacted 1 passage
Active Submissions p. p. 23
Active Submissions Total A - Technical Evaluation A-1 - Adherence to RFP requirements A-2 - Ongoing support availability and service levels A-3 - Speed and efficiency of implementation (or project) plan, availability, and delivery the indu...

AI summary The text discusses the evaluation criteria for technical submissions, focusing on adherence to RFP requirements, resource availability, implementation plans, and expertise. It highlights the need for specialized expertise and the gap in internal resource availability for the MDMS Module Updates project.

N-4NSPI (REI) RIR 1 to 22 2 passages
p. p. 36
Request IR-10: (a) 1 (e) Please explain whether the referenced "increase in technical requirements for 2 forecasted generation data integration" were driven in whole or in part by 3 cybersecurity incident remediation needs and provide supp...

AI summary The response to Request IR-10 clarifies that the increase in technical requirements for forecasted generation data integration was not influenced by cybersecurity incident remediation. The response also explains that project costs related to the Renewable to Retail (RtR) implementation are being tracked separately from cybersecurity incident costs.

Date Filed: March 3, 2026 NSPI (REI) IR-13 Page 3 of 3 p. p. 36
Date Filed: March 3, 2026 NSPI (REI) IR-13 Page 3 of 3 1 Request IR-14: 11 business process and technical set up work possible ahead of final commissioning 12 and COD, and in the interest of avoiding additional costs to be incurred, the pr...

AI summary The document outlines a request (IR-14) related to the Renewable to Retail (RtR) Project, specifying that business process and technical setup work should be delayed until seven months before the first retail sales are confirmed. It also notes that costs are organized by resource rather than deliverable and describes the monthly data delivery process to the Licensed Retail Supplier (LRS) via NS Power's secure SFTP server.

Disclaimer: These summaries were generated by AI from the filings they describe. We take care to make them accurate, but errors are possible - and they aren't advice. Only the filings themselves are the record: if you're relying on something here, confirm it against the source documents or the Nova Scotia Energy Board's own record. Full disclaimer →