100502NSEB (NSPI) IR-1 to IR-22 - WORD
4 passages
to manage the non-AGC IPPs, to ensure efficiency, accuracy and transparency. 3. Please explain the requirements for IPPs to connect to AGC. 4. Please provide a cost benefit analysis of the AGC system. Please explain the AGC function in pla...
AI summary The text outlines a series of questions related to the Automatic Generator Control (AGC) system, including its function, cost-benefit analysis, integration with Independent Power Producers (IPPs), and the project's relationship with previous applications. It also inquires about Request for Proposals (RFP) status, user involvement, and the rationale for the project.
in NS Power’s plan to transfer the assets and indicate any training requirements for NSIESO. 4. If NS Power is the only user, please explain why. In Why do this project, NS Power noted the following: Legacy wind generators are not equipped...
AI summary The document outlines NS Power’s proposal to implement AGC capabilities for legacy wind generators, enabling more efficient dispatch and compensation. It requests clarification on mandatory requirements, compensation terms, and fairness in curtailing both legacy and new IPPs. The project aims to improve data handling and automation for better reconciliation and settlement processes.
1. For the automated wind curtailment, please explain how the new system integrates with other generation resources (non wind generators and non AGC wind generators) to receive dynamic generation and consumption data to perform this functi...
AI summary The text consists of a series of questions raised in a regulatory proceeding regarding the automation system for wind curtailment, its integration with other generation resources, system upgrades, costs, lifecycle, maintenance, and financial implications. It also asks about funding from NRCan and contingency plans in case of system failure.
unavailable during operation. 15. If yes, please describe how ECC would operate during the absence of the automation system. 16. If contingency plans are not available, please provide an explanation. Please describe the activities NS Power...
AI summary The document raises questions about NS Power's contingency plans for the absence of an automation system, the economic analysis of not installing it, and the justification for consulting services. It also requests details on similar projects and the breakdown of tasks and responsibilities.