3.4. Bottom Brook Converter and Switchyard Site
p. pp. 18-19
3.4. Bottom Brook Converter and Switchyard Site - The facilities have been well maintained and are in good order. - Reactor hall door experienced heat induced buckling that initiated a 'door open' trip. Solutions to improve reliability of...
AI summary The Bottom Brook Converter and Switchyard Site facilities are in good condition, though a reactor hall door issue caused a trip. Solutions are being explored to improve reliability. The SPS installation is complete, and new GIC sensors have been installed to monitor GIC effects on the converter transformer fleet.