Home›Energy Storage›M13014›Evidence
Topic/Matter Intersection

Topic:"Energy Storage" in M13014

Matter: Nova Scotia Power Inc. - CI C0068719 - IT - Distributed Intelligence Apps - $3,165,790
7 passages 3 documents

Energy Storage across all matters →

N-2NSPI (NSEB) RIR 1 to 15 - Redacted 5 passages
Location Awareness p. pp. 39-40
Location Awareness Production - » Function: Determines connectivity of meter to transformers, phases, and feeders utilizing PLC and RF peer-to-peer - » Benefits: Maintain up-to-date grid topology awareness for DI and back-office utility sy...

AI summary Location Awareness functionality determines the connectivity of meters to transformers, phases, and feeders using PLC and RF peer-to-peer communication. Benefits include maintaining grid topology awareness, advanced transformer management, storm simulation, DER analytics, and accurate asset loading and planning.

» Benefits: p. p. 44
» Benefits: - Preserve transformer lifetime - Reduce unplanned outages - Reduced network traffic through use of spokesmeters - More effective programs (e.g. VVO/CVR) or better resolution control (e.g. load flow)

AI summary The benefits outlined include preserving transformer lifetime, reducing unplanned outages, decreasing network traffic with spokesmeters, and enabling more effective programs like VVO/CVR and better resolution control such as load flow.

Distribution Operations, Distribution & Strategic Planning p. p. 49
Distribution Operations, Distribution & Strategic Planning You want to know what your real-time large controllable and uncontrollable EV loads are, down to a transformer level. It would be great to feed this information automatically into...

AI summary The text discusses the need for real-time monitoring of large controllable and uncontrollable EV loads at the transformer level, with the intention of automatically feeding this data into a DERMS or other control systems to prevent overloading.

» Benefits: p. p. 59
» Benefits: - Input to solar generation models for more accurate planning studies - Protection of distribution transformers in conjunction with real-time control systems

AI summary The benefits discussed include improved accuracy in solar generation planning studies and protection of distribution transformers through real-time control systems.

CI C0068719 - IT - Distributed Intelligence Apps (NSEB M13014) NSPI Responses to NSEB Information Requests p. p. 63
CI C0068719 - IT - Distributed Intelligence Apps (NSEB M13014) NSPI Responses to NSEB Information Requests 1 Request IR-13: EV Awareness Distribution Grid Situational Awareness Provides near-real-time disaggregation information for when an...

AI summary The document discusses NSPI's response to an information request regarding EV awareness and distribution grid situational awareness. It highlights the limitations of current systems in providing near-real-time visibility into EV charging behavior and notes that no active programs currently offer this capability.

104028Decision letter 1 passage
CI C0068719 - IT - Distributed Intelligence Apps - $3,165,790
CI C0068719 - IT - Distributed Intelligence Apps - $3,165,790 This project was originally included in the 2026 Annual Capital Expenditure (ACE) Plan at a cost of $2,637,356. The estimate subsequently increased by $528,434 following additio...

AI summary NS Power is requesting $3,165,790 for a pilot project to evaluate Distributed Intelligence (DI) Apps, which aim to improve operational efficiency and safety. The project is compatible with existing Advanced Metering Infrastructure (AMI) and supported by funding from Natural Resources Canada. The Board approves the request, citing its potential to enhance grid reliability and support provincial energy goals.

104028Decision letter 1 passage
CI C0068719 - IT - Distributed Intelligence Apps - $3,165,790
CI C0068719 - IT - Distributed Intelligence Apps - $3,165,790 This project was originally included in the 2026 Annual Capital Expenditure (ACE) Plan at a cost of $2,637,356. The estimate subsequently increased by $528,434 following additio...

AI summary NS Power is requesting approval for a $3,165,790 project to pilot Distributed Intelligence (DI) Apps, which aim to improve operational efficiency and grid reliability. The project is supported by Natural Resources Canada's Energy Innovation Program and is compatible with existing Advanced Metering Infrastructure. The Board has accepted the project as necessary and justified, approving the requested funds.

Disclaimer: These summaries were generated by AI from the filings they describe. We take care to make them accurate, but errors are possible - and they aren't advice. Only the filings themselves are the record: if you're relying on something here, confirm it against the source documents or the Nova Scotia Energy Board's own record. Full disclaimer →