M-2NSPI DRO Decision - Redacted
1 passage
curacy test, performed by N.S.Power in their Measurement Canada accredited meter shop, followed by a meter test by Measurement Canada if the Customer wishes to have an independent meter test performed Meter test results indicate that meter...
AI summary The Dispute Resolution Officer (DRO) has ruled that N.S. Power's meter test results are accurate, and the customer has been appropriately billed. The customer has the option to request an independent test by Measurement Canada if they remain unsatisfied with the results.
M-6MEADE (NSEB) RIR-1 to RIR-3 (redacted)
1 passage
IR-3(A) Have you considered that cold winter temperatures during November to March could have caused an increase in your electricity consumption?
AI summary The question raised in IR-3(A) asks whether cold winter temperatures from November to March could have caused an increase in electricity consumption, suggesting a potential link between weather conditions and energy usage patterns.
Disclaimer: These summaries were generated by AI from the filings they describe. We take care to make them accurate, but errors are possible - and they aren't advice. Only the filings themselves are the record: if you're relying on something here, confirm it against the source documents or the Nova Scotia Energy Board's own record. Full disclaimer →