Option 2 Remove the old 4 kV cables 1H-243, 1H-246 and 1H-247 (#500, 3 phase PILC) along the Lower Water, Sackville and Granville Streets between 1H and MH46 (1 km). Install new cables in the freed-up ducts while the existing feeder cables...
AI summary Option 2 proposes replacing aging 4 kV cables along specific streets while maintaining service via existing feeders, freeing ducts for future upgrades, and salvaging old equipment. It addresses PCB management in cables, referencing environmental regulations. The plan avoids alternative supply for 90% of the radial section but requires temporary alternatives for the remaining segment due to insufficient duct space.