Matter: To obtain a cost reasonableness review of NS Power - CI C0051815 – $5,959,515 - RTU Replacements Program – Phase 6, as outlined in Section 2.1 of the ACE 2025 decision (M12012)
1 passage 1 document

Environmental Compliance across all matters →

N-2NSPI (Midgard) RIR 1 to 14 - Redacted 1 passage
7.3.6. Environmental Considerations p. p. 86
7.3.6. Environmental Considerations a. The Contractor's past environmental performance will be included in the review prior to the contract. Past NSPI Contractor Performance Evaluation forms will be considered prior to the awarding of a co...

AI summary The Contractor's past environmental performance, including NSPI Contractor Performance Evaluation forms, will be reviewed prior to the awarding of a contract.

Disclaimer: These summaries were generated by AI from the filings they describe. We take care to make them accurate, but errors are possible - and they aren't advice. Only the filings themselves are the record: if you're relying on something here, confirm it against the source documents or the Nova Scotia Energy Board's own record. Full disclaimer →