N-12026 10-Year System Outlook Report 2 passages
3.2 Changes in Capacity p. pp. 10-12
3.2 Changes in Capacity The basis for the 2026 10-Year System Outlook resource plan is the Government of Nova Scotia's 2030 Clean Power Plan and NS Power's Evergreen IRP scenario CE1-E1-R2 (net zero 2035, current policy and trends electrif...

AI summary The 2026 10-Year System Outlook resource plan is based on the Government of Nova Scotia's 2030 Clean Power Plan and NS Power's Evergreen IRP scenario. It anticipates a net increase in installed capacity of 2,804 MW and firm capacity of 370 MW over the next 10 years, supporting decarbonization goals and 80% renewable energy electricity sales by 2030.

3.2.4 Fast-Acting Generation p. pp. 13-14
3.2.4 Fast-Acting Generation IESO Nova Scotia has initiated a procurement process for 300 to 600 MW of fast-acting generation capacity for the province. The draft Request for Proposals (RFP) and Tolling Agreement was made available for pro...

AI summary IESO Nova Scotia has initiated a procurement process for 300 to 600 MW of fast-acting generation to support the province's clean energy transition. This capacity is critical for maintaining supply reliability as renewable energy penetration increases and peak demand grows. The 2026 10-Year Outlook Resource Plan includes 450 MW of fast-acting generation, with additional needs identified by 2035/2036.

N-7IESO (SBA) RIR 1 to 22 1 passage
Request IR – 16 p. p. 22
Request IR – 16 - Refer to the 2026 Report Section 4.3 Clean Electricity Regulations (CER), page 21. - Specifically considering the treatment of new fast-acting generation under the CER: - a) Please describe IESO NS's current assessment of...

AI summary The text requests the IESO NS to assess whether 450 MW of new fast-acting generation qualifies as a 'Planned Resource' under the Clean Electricity Regulations (CER), provide updated analysis on emissions performance standards, and describe implications for resource plans if the generation is not eligible as a Planned Resource.

103636IG (IESO) IR 1 to 4 1 passage
1 synchronous condenser requirements presented in the report.
1 synchronous condenser requirements presented in the report. 2 (c) Please explain whether any such expansion or acceleration would affect 3 the 300 to 400 MW battery storage capacity target under the Government 4 of Nova Scotia's Clean Po...

AI summary The document asks whether the expansion or acceleration of synchronous condenser requirements would impact the 300 to 400 MW battery storage capacity target under the Government of Nova Scotia's Clean Power Plan or the timing for achieving that target.

104074Submissions - SBA 1 passage
5. Environmental Policy Compliance
5. Environmental Policy Compliance In reviewing the System Outlook and planned additions, the SBA has identified areas of uncertainty in the plan regarding environmental policy compliance. First, in response to an IR from the SBA, IESO Nov...

AI summary The SBA has raised concerns about environmental policy compliance in the System Outlook and planned additions. IESO Nova Scotia notes uncertainty regarding whether new fast-acting generation units will qualify as 'planned units' under Clean Electricity Regulations, which could impose emissions limitations. The SBA argues this may affect operating hours and long-term resource mix economics. Delays in the Reliability Intertie project may also increase decarbonization costs.

Disclaimer: These summaries were generated by AI from the filings they describe. We take care to make them accurate, but errors are possible - and they aren't advice. Only the filings themselves are the record: if you're relying on something here, confirm it against the source documents or the Nova Scotia Energy Board's own record. Full disclaimer →