3.2 Changes in Capacity The basis for the 2026 10-Year System Outlook resource plan is the Government of Nova Scotia's 2030 Clean Power Plan and NS Power's Evergreen IRP scenario CE1-E1-R2 (net zero 2035, current policy and trends electrif...
AI summary The 2026 10-Year System Outlook resource plan is based on the Government of Nova Scotia's 2030 Clean Power Plan and NS Power's Evergreen IRP scenario. It anticipates a net increase in installed capacity of 2,804 MW and firm capacity of 370 MW over the next 10 years, supporting decarbonization goals and 80% renewable energy electricity sales by 2030.
3.2.4 Fast-Acting Generation IESO Nova Scotia has initiated a procurement process for 300 to 600 MW of fast-acting generation capacity for the province. The draft Request for Proposals (RFP) and Tolling Agreement was made available for pro...
AI summary IESO Nova Scotia has initiated a procurement process for 300 to 600 MW of fast-acting generation to support the province's clean energy transition. This capacity is critical for maintaining supply reliability as renewable energy penetration increases and peak demand grows. The 2026 10-Year Outlook Resource Plan includes 450 MW of fast-acting generation, with additional needs identified by 2035/2036.